Home / Projects / AG CENTRAL
Latest DLD inspection photo of AG CENTRAL
Latest inspection · 2026-02-09 · DLD inspection
Planned handover2026-10-31
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2023-10-31
in the DLD registry
Today
50.8%
last inspected 2026-01-26
Pace forecast
Day 2 of 7
unlocks as daily tracking accrues
Planned handover
2026-10-31
developer's official date

Watch it rise — one frame per DLD inspection

AG CENTRAL on 2023-09-18
2023-09-18 · 2.3% complete
1 / 5

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
AG PROPERTIES L.L.C
Area
Wadi Al Safa 5
Master project
Project type
Normal
Start date
2023-10-31
Planned handover
2026-10-31
Last inspection
2026-01-26
Project value
AED 34.0M
Units
99
Villas
0
Buildings
0
DLD project number
2422

AG CENTRAL: frequently asked questions — answers update daily from registry data

When will AG CENTRAL be handed over?
The developer's planned handover for AG CENTRAL is 2026-10-31; construction is currently 51% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on AG CENTRAL?
AG CENTRAL is 50.8% complete according to the Dubai Land Department's inspection of 2026-01-26.
Is AG CENTRAL delayed?
As of today, AG CENTRAL has not passed its planned handover date of 2026-10-31. We compare the official date against the calendar daily and record every change on this page.
Who is the developer of AG CENTRAL, and do they deliver on time?
AG CENTRAL is developed by AG PROPERTIES L.L.C. On our Developer Reliability Index they score 92/100 (A On schedule), based on how much of their active portfolio is past its planned handover in the official registry.
Where is AG CENTRAL located?
AG CENTRAL is located in Wadi Al Safa 5, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in AG CENTRAL?
AG CENTRAL comprises 99 units (normal), per the DLD registry.
Can I see real construction photos of AG CENTRAL?
Yes — this page carries 30 official construction photos taken during Dubai Land Department inspections, newest from 2026-02-09, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in AG CENTRAL?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
How do I get alerts when something changes on AG CENTRAL?
Use the free Track this project form on this page. We check the official registry every day and email you the moment AG CENTRAL's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE50.8%2026-10-31
2026-08-05ACTIVE50.8%2026-10-31
2026-08-06ACTIVE50.8%2026-10-31
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.
Track AG CENTRAL