Home / Projects / A 99
Latest DLD inspection photo of A 99
Latest inspection · 2026-07-01 · DLD inspection
Planned handover2026-10-31
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2023-10-31
in the DLD registry
Today
45.1%
last inspected 2026-06-24
Pace forecast
Day 2 of 7
unlocks as daily tracking accrues
Planned handover
2026-10-31
developer's official date

Watch it rise — one frame per DLD inspection

A 99 on 2024-05-01
2024-05-01 · 0.3% complete
1 / 6

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
ARABIAN GULF PROPERTIES
Area
Wadi Al Safa 5
Master project
Project type
Normal
Start date
2023-10-31
Planned handover
2026-10-31
Last inspection
2026-06-24
Project value
AED 42.1M
Units
90
Villas
0
Buildings
0
DLD project number
2768

A 99: frequently asked questions — answers update daily from registry data

When will A 99 be handed over?
The developer's planned handover for A 99 is 2026-10-31; construction is currently 45% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on A 99?
A 99 is 45.1% complete according to the Dubai Land Department's inspection of 2026-06-24.
Is A 99 delayed?
As of today, A 99 has not passed its planned handover date of 2026-10-31. We compare the official date against the calendar daily and record every change on this page.
Who is the developer of A 99, and do they deliver on time?
A 99 is developed by ARABIAN GULF PROPERTIES. On our Developer Reliability Index they score 92/100 (A On schedule), based on how much of their active portfolio is past its planned handover in the official registry.
Where is A 99 located?
A 99 is located in Wadi Al Safa 5, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in A 99?
A 99 comprises 90 units (normal), per the DLD registry.
Can I see real construction photos of A 99?
Yes — this page carries 36 official construction photos taken during Dubai Land Department inspections, newest from 2026-07-01, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in A 99?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
How do I get alerts when something changes on A 99?
Use the free Track this project form on this page. We check the official registry every day and email you the moment A 99's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE45.1%2026-10-31
2026-08-05ACTIVE45.1%2026-10-31
2026-08-06ACTIVE45.1%2026-10-31
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.
Track A 99