Latest DLD inspection photo of VUE DU LAC
Latest inspection · 2014-01-06 · DLD inspection
Planned handover2014-10-01
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2023-05-01
in the DLD registry
Today
6.0%
last inspected 2013-12-17
Pace forecast
Day 2 of 7
unlocks as daily tracking accrues
Planned handover
2014-10-01
developer's official date

Watch it rise — one frame per DLD inspection

VUE DU LAC on 2012-06-10
2012-06-10 · 10.0% complete
1 / 4

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
MAG PALACE PROPERTIES DEVELOPMENT L.L.C
Area
Al Thanyah Fifth
Master project
Project type
Normal
Start date
2023-05-01
Planned handover
2014-10-01
Last inspection
2013-12-17
Project value
AED 1
Units
0
Villas
0
Buildings
0
DLD project number
459

VUE DU LAC: frequently asked questions — answers update daily from registry data

When will VUE DU LAC be handed over?
The developer's planned handover for VUE DU LAC is 2014-10-01; construction is currently 6% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on VUE DU LAC?
VUE DU LAC is 6.0% complete according to the Dubai Land Department's inspection of 2013-12-17.
Who is the developer of VUE DU LAC, and do they deliver on time?
VUE DU LAC is developed by MAG PALACE PROPERTIES DEVELOPMENT L.L.C.
Where is VUE DU LAC located?
VUE DU LAC is located in Al Thanyah Fifth, Dubai. See every project in the area, plus prices and rents, on the area page.
Can I see real construction photos of VUE DU LAC?
Yes — this page carries 17 official construction photos taken during Dubai Land Department inspections, newest from 2014-01-06, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in VUE DU LAC?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
How do I get alerts when something changes on VUE DU LAC?
Use the free Track this project form on this page. We check the official registry every day and email you the moment VUE DU LAC's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04CONDITIONAL_ACTIVATING6.0%2014-10-01
2026-08-05CONDITIONAL_ACTIVATING6.0%2014-10-01
2026-08-06CONDITIONAL_ACTIVATING6.0%2014-10-01
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.