Home / Projects / THE MELGRANO
Latest DLD inspection photo of THE MELGRANO
Latest inspection · 2026-06-18 · DLD inspection
Planned handover2026-12-31
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2024-11-01
in the DLD registry
Today
32.0%
last inspected 2026-06-16
Pace forecast
Day 7 of 7
unlocks as daily tracking accrues
Planned handover
2026-12-31
developer's official date

How THE MELGRANO compares

Similar off-plan projects in Jumeirah Second — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about THE MELGRANO

Considering buying in THE MELGRANO? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Watch it rise — one frame per DLD inspection

THE MELGRANO on 2023-10-26
2023-10-26 · 0.0% complete
1 / 7

Building & unit mix — from DLD project records

10
Floors
14
Total units
1
Building
UsageUnit typeUnits
CommercialUnspecified1
Residential4 B/R6
Residential5 B/R7

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
THE MELGRANO REAL ESTATE DEVELOPMENT L.L.C
Area
Jumeirah Second
Master project
Project type
Normal
Start date
2024-11-01
Planned handover
2026-12-31
Last inspection
2026-06-16
Project value
AED 220.0M
Units
14
Villas
0
Buildings
0
DLD project number
2759

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
2759
Registered with DLD
2024-11-26
Regulator
Dubai Municipality
Escrow account no.
12943343920002

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Jumeirah Second · See every project on the construction map →

THE MELGRANO: frequently asked questions — answers update daily from registry data

When will THE MELGRANO be handed over?
The developer's planned handover for THE MELGRANO is 2026-12-31; construction is currently 32% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on THE MELGRANO?
THE MELGRANO is 32.0% complete according to the Dubai Land Department's inspection of 2026-06-16.
Is THE MELGRANO delayed?
As of today, THE MELGRANO has not passed its planned handover date of 2026-12-31. We compare the official date against the calendar daily and record every change on this page.
Who is the developer of THE MELGRANO, and do they deliver on time?
THE MELGRANO is developed by THE MELGRANO REAL ESTATE DEVELOPMENT L.L.C. On our Developer Reliability Index they score 89/100 (A On schedule), based on how much of their active portfolio is past its planned handover in the official registry.
Where is THE MELGRANO located?
THE MELGRANO is located in Jumeirah Second, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in THE MELGRANO?
THE MELGRANO comprises 14 units (normal), per the DLD registry.
Can I see real construction photos of THE MELGRANO?
Yes — this page carries 30 official construction photos taken during Dubai Land Department inspections, newest from 2026-06-18, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in THE MELGRANO?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for THE MELGRANO go?
Only into the project's DLD-registered escrow account (no. 12943343920002). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on THE MELGRANO?
Use the free Track this project form on this page. We check the official registry every day and email you the moment THE MELGRANO's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE32.0%2026-12-31
2026-08-05ACTIVE32.0%2026-12-31
2026-08-06ACTIVE32.0%2026-12-31
2026-08-08ACTIVE32.0%2026-12-31
2026-08-09ACTIVE32.0%2026-12-31
2026-08-10ACTIVE32.0%2026-12-31
2026-08-11ACTIVE32.0%2026-12-31
2026-08-12ACTIVE32.0%2026-12-31
2026-08-13ACTIVE32.0%2026-12-31
2026-08-14ACTIVE32.0%2026-12-31
2026-08-15ACTIVE32.0%2026-12-31
2026-08-16ACTIVE32.0%2026-12-31
2026-08-17ACTIVE32.0%2026-12-31
2026-08-18ACTIVE32.0%2026-12-31
2026-08-19ACTIVE32.0%2026-12-31
2026-08-20ACTIVE32.0%2026-12-31
2026-08-21ACTIVE32.0%2026-12-31
2026-08-22ACTIVE32.0%2026-12-31
2026-08-23ACTIVE32.0%2026-12-31
2026-08-24ACTIVE32.0%2026-12-31
2026-08-25ACTIVE32.0%2026-12-31
2026-08-26ACTIVE32.0%2026-12-31
2026-08-27ACTIVE32.0%2026-12-31
2026-08-28ACTIVE32.0%2026-12-31
2026-08-29ACTIVE32.0%2026-12-31
2026-08-30ACTIVE32.0%2026-12-31
2026-08-31ACTIVE32.0%2026-12-31
2026-09-01ACTIVE32.0%2026-12-31
2026-09-02ACTIVE32.0%2026-12-31
2026-09-03ACTIVE32.0%2026-12-31
2026-09-04ACTIVE32.0%2026-12-31
2026-09-05ACTIVE32.0%2026-12-31
2026-09-06ACTIVE32.0%2026-12-31
2026-09-07ACTIVE32.0%2026-12-31
2026-09-08ACTIVE32.0%2026-12-31
2026-09-09ACTIVE32.0%2026-12-31
2026-09-10ACTIVE32.0%2026-12-31
2026-09-11ACTIVE32.0%2026-12-31
2026-09-12ACTIVE32.0%2026-12-31
2026-09-13ACTIVE32.0%2026-12-31
2026-09-14ACTIVE32.0%2026-12-31
2026-09-15ACTIVE32.0%2026-12-31
2026-09-16ACTIVE32.0%2026-12-31
2026-09-17ACTIVE32.0%2026-12-31
2026-09-18ACTIVE32.0%2026-12-31
2026-09-19ACTIVE32.0%2026-12-31
2026-09-20ACTIVE32.0%2026-12-31
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.
Track THE MELGRANO