10%complete
Planned handover2027-12-05
SourceDLD · daily
The road to keys — registry facts, our forecast
Registered start
2026-03-16
in the DLD registry
Today
10.4%
last inspected 2026-08-21
At the current pace
…
…
Planned handover
2027-12-05
developer's official date
How Sea Mirror Residences compares
Similar off-plan projects in Jumeirah Second — compare progress, handover and developer.
Track this project
Get an email the moment DLD reports a change — construction progress, a status change, or a handover date that moves.
One click. Creates your free account — no password, ever.
Ready to take the next step?
Talk to a verified agent about Sea Mirror Residences
Considering buying in Sea Mirror Residences? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.
or register your interest below
Project facts
Developer
LAMAR DEVELOPMENT L.L.C
Area
Jumeirah Second
Master project
—
Project type
Normal
Start date
2026-03-16
Planned handover
2027-12-05
Last inspection
2026-08-21
Project value
AED 320.0M
Units
19
Villas
0
Buildings
0
DLD project number
3273
Registration & escrow — verify before you pay anyone
DLD / RERA project no.
3273
No escrow account is recorded in the registry for this project yet — normal while a project is still PENDING activation. Treat any payment request with extra caution until one exists.
Sea Mirror Residences: frequently asked questions — answers update daily from registry data
When will Sea Mirror Residences be handed over?
The developer's planned handover for Sea Mirror Residences is 2027-12-05; construction is currently 10% complete. At the observed construction pace, our independent forecast is 2029-12-13.
How far along is construction on Sea Mirror Residences?
Sea Mirror Residences is 10.4% complete according to the Dubai Land Department's inspection of 2026-08-21.
Who is the developer of Sea Mirror Residences, and do they deliver on time?
Sea Mirror Residences is developed by LAMAR DEVELOPMENT L.L.C. On our Developer Reliability Index they score 89/100 (A — On schedule), based on how much of their active portfolio is past its planned handover in the official registry.
Where is Sea Mirror Residences located?
Sea Mirror Residences is located in Jumeirah Second, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Sea Mirror Residences?
Sea Mirror Residences comprises 19 units (normal), per the DLD registry.
Is my money safe if I buy in Sea Mirror Residences?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
How do I get alerts when something changes on Sea Mirror Residences?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Sea Mirror Residences's progress, status, or planned handover date changes.
Progress history — one row per official DLD snapshot
| Snapshot date | Status | Complete | Planned handover |
|---|---|---|---|
| 2026-08-04 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-05 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-06 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-08 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-09 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-10 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-11 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-12 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-13 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-14 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-15 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-16 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-17 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-18 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-19 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-20 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-21 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-22 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-23 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-24 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-25 | PENDING | 6.9% | 2027-12-05 |
| 2026-08-26 | PENDING | 10.4% | 2027-12-05 |
| 2026-08-27 | PENDING | 10.4% | 2027-12-05 |
| 2026-08-28 | PENDING | 10.4% | 2027-12-05 |
| 2026-08-29 | PENDING | 10.4% | 2027-12-05 |
| 2026-08-30 | PENDING | 10.4% | 2027-12-05 |
| 2026-08-31 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-01 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-02 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-03 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-04 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-05 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-06 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-07 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-08 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-09 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-10 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-11 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-12 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-13 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-14 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-15 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-16 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-17 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-18 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-19 | PENDING | 10.4% | 2027-12-05 |
| 2026-09-20 | PENDING | 10.4% | 2027-12-05 |
Change events
| Detected | Event | Change |
|---|---|---|
| 2026-08-26 | PROGRESS | 6.86 → 10.41 |
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.