Latest inspection · 2026-03-10 · DLD inspection
Planned handover2026-03-13
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2023-03-27
in the DLD registry
Today
100.0%
last inspected 2026-03-04
Pace forecast
Day 7 of 7
unlocks as daily tracking accrues
Planned handover
2026-03-13
developer's official date

How The Valley - Elora compares

Similar off-plan projects in Al Yufrah 1 — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about The Valley - Elora

Considering buying in The Valley - Elora? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Watch it rise — one frame per DLD inspection

The Valley - Elora on 2022-11-16
2022-11-16 · 0.0% complete
1 / 10

Building & unit mix — from DLD project records

—
Floors
430
Total units
—
Buildings
UsageUnit typeUnits
Residential3 B/R284
Residential4 B/R146

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Real sale prices — 99 registered DLD sales since 2026-01-22

AED 1,407/sqft
Median sale price
99
Registered sales
99
Sales, last 12 months
Unit typeSalesMedian AED/sqftMedian price
4 B/R551,407AED 3.5M
3 B/R441,735AED 2.6M

Source: DLD registered sale transactions for this project.

Prices by unit size — vs the Al Yufrah 1 average

BedsUnits soldSize rangeMedian priceAED/sqftArea avgPremium vs area
3 B/R441,481–1,484 sqftAED 2.6M1,7351,569+11%
4 B/R552,470–3,305 sqftAED 3.5M1,4071,244+13%

Median AED/sqft of DLD-registered sales in this project vs all sales in Al Yufrah 1 for the same unit type. “Premium vs area” is how much more (or less) buyers pay here than the neighbourhood average.

Sale price history — 606 sales, median AED/sqft by year

+46% median price growth from 2023 to 2026 · 97% of sales were off-plan

YearMedian AED/sqftSalesYear-on-yearSince launch
2023launch1,109422——
20241,23384+11%+11%
20251,51775+23%+37%
20261,61725+7%+46%

Median AED/sqft of DLD-registered sales each year (years with 3+ sales); the earliest year on record approximates launch pricing. “Year-on-year” compares each year to the one before it, “since launch” to the first year. Source: Dubai Land Department transaction records.

Available layouts — check current availability & price

Layouts registered in The Valley - Elora, grouped by size. We’ll confirm current availability, floor and price with a RERA-licensed agent — we don’t hold live developer inventory, so these are representative configurations, not a live unit list.

BedsSizeTypical priceAED/sqftRegistered
3 B/R1,483 sqftAED 2.6M1,73544
4 B/R2,487 sqftAED 3.5M1,40742
4 B/R2,488 sqftAED 3.4M1,3473
4 B/R2,616 sqftAED 3.3M1,2544
4 B/R2,708 sqftAED 3.0M1,1261
4 B/R2,713 sqftAED 3.3M1,2072
4 B/R3,196 sqftAED 3.5M1,0951
4 B/R3,282 sqftAED 3.5M1,0741
4 B/R3,305 sqftAED 3.2M9681

Recent registered sales — individual DLD transactions, newest first

DateBedsSizePriceAED/sqftType
2026-11-184 B/R2,486 sqftAED 3.3M1,327Resale
2026-11-113 B/R1,483 sqftAED 2.7M1,821Resale
2026-11-063 B/R1,483 sqftAED 2.6M1,721Resale
2026-11-053 B/R1,483 sqftAED 2.5M1,686Resale
2026-11-033 B/R1,483 sqftAED 2.6M1,787Resale
2026-10-304 B/R2,488 sqftAED 2.1M851Resale
2026-10-293 B/R1,483 sqftAED 2.5M1,686Resale
2026-10-293 B/R1,484 sqftAED 2.7M1,819Resale
2026-10-283 B/R1,481 sqftAED 2.7M1,823Resale
2026-10-203 B/R1,483 sqftAED 2.5M1,676Resale
2026-10-203 B/R1,483 sqftAED 2.5M1,703Resale
2026-10-193 B/R1,482 sqftAED 2.5M1,654Resale
2026-10-193 B/R1,483 sqftAED 2.7M1,841Resale
2026-10-193 B/R1,482 sqftAED 2.5M1,721Resale
2026-10-154 B/R2,487 sqftAED 3.5M1,407Resale
2026-10-153 B/R1,483 sqftAED 2.8M1,888Resale
2026-10-143 B/R1,483 sqftAED 2.7M1,821Resale
2026-10-133 B/R1,483 sqftAED 2.6M1,753Resale
2026-10-093 B/R1,482 sqftAED 2.6M1,789Resale
2026-10-073 B/R1,483 sqftAED 2.7M1,844Resale
2026-10-053 B/R1,483 sqftAED 2.5M1,686Resale
2026-10-023 B/R1,482 sqftAED 2.6M1,789Resale
2026-10-013 B/R1,481 sqftAED 2.5M1,667Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale
2026-09-304 B/R2,487 sqftAED 3.5M1,407Resale

Source: DLD registered sale transactions. Floor and unit numbers aren’t published in the public transaction feed, so they’re not shown.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
EMAAR DEVELOPMENT P.J.S.C.
Area
Al Yufrah 1
Master project
—
Project type
Normal
Start date
2023-03-27
Planned handover
2026-03-13
Last inspection
2026-03-04
Project value
AED 336.4M
Units
0
Villas
430
Buildings
0
DLD project number
2511

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
2511
Registered with DLD
2023-01-10
Regulator
Dubai Development Authority (DDA)
Escrow account no.
001582307635701

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Al Yufrah 1 · See every project on the construction map →

The Valley - Elora: frequently asked questions — answers update daily from registry data

When will The Valley - Elora be handed over?
The developer's planned handover for The Valley - Elora is 2026-03-13; construction is currently 100% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on The Valley - Elora?
The Valley - Elora is 100.0% complete according to the Dubai Land Department's inspection of 2026-03-04.
Who is the developer of The Valley - Elora, and do they deliver on time?
The Valley - Elora is developed by EMAAR DEVELOPMENT P.J.S.C.. On our Developer Reliability Index they score 97/100 (A — On schedule), based on how much of their active portfolio is past its planned handover in the official registry.
What are real sale prices in The Valley - Elora?
Registered DLD sales in The Valley - Elora show a median of AED 1,407/sqft across 99 transactions since 2026-01-22. These are actual registered sales, not asking prices — the full breakdown is on this page.
Where is The Valley - Elora located?
The Valley - Elora is located in Al Yufrah 1, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in The Valley - Elora?
The Valley - Elora comprises 430 villas (normal), per the DLD registry.
Can I see real construction photos of The Valley - Elora?
Yes — this page carries 67 official construction photos taken during Dubai Land Department inspections, newest from 2026-03-10, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in The Valley - Elora?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for The Valley - Elora go?
Only into the project's DLD-registered escrow account (no. 001582307635701). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on The Valley - Elora?
Use the free Track this project form on this page. We check the official registry every day and email you the moment The Valley - Elora's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04FINISHED100.0%2026-03-13
2026-08-05FINISHED100.0%2026-03-13
2026-08-06FINISHED100.0%2026-03-13
2026-08-08FINISHED100.0%2026-03-13
2026-08-09FINISHED100.0%2026-03-13
2026-08-10FINISHED100.0%2026-03-13
2026-08-11FINISHED100.0%2026-03-13
2026-08-12FINISHED100.0%2026-03-13
2026-08-13FINISHED100.0%2026-03-13
2026-08-14FINISHED100.0%2026-03-13
2026-08-15FINISHED100.0%2026-03-13
2026-08-16FINISHED100.0%2026-03-13
2026-08-17FINISHED100.0%2026-03-13
2026-08-18FINISHED100.0%2026-03-13
2026-08-19FINISHED100.0%2026-03-13
2026-08-20FINISHED100.0%2026-03-13
2026-08-21FINISHED100.0%2026-03-13
2026-08-22FINISHED100.0%2026-03-13
2026-08-23FINISHED100.0%2026-03-13
2026-08-24FINISHED100.0%2026-03-13
2026-08-25FINISHED100.0%2026-03-13
2026-08-26FINISHED100.0%2026-03-13
2026-08-27FINISHED100.0%2026-03-13
2026-08-28FINISHED100.0%2026-03-13
2026-08-29FINISHED100.0%2026-03-13
2026-08-30FINISHED100.0%2026-03-13
2026-08-31FINISHED100.0%2026-03-13
2026-09-01FINISHED100.0%2026-03-13
2026-09-02FINISHED100.0%2026-03-13
2026-09-03FINISHED100.0%2026-03-13
2026-09-04FINISHED100.0%2026-03-13
2026-09-05FINISHED100.0%2026-03-13
2026-09-06FINISHED100.0%2026-03-13
2026-09-07FINISHED100.0%2026-03-13
2026-09-08FINISHED100.0%2026-03-13
2026-09-09FINISHED100.0%2026-03-13
2026-09-10FINISHED100.0%2026-03-13
2026-09-11FINISHED100.0%2026-03-13
2026-09-12FINISHED100.0%2026-03-13
2026-09-13FINISHED100.0%2026-03-13
2026-09-14FINISHED100.0%2026-03-13
2026-09-15FINISHED100.0%2026-03-13
2026-09-16FINISHED100.0%2026-03-13
2026-09-17FINISHED100.0%2026-03-13
2026-09-18FINISHED100.0%2026-03-13
2026-09-19FINISHED100.0%2026-03-13
2026-09-20FINISHED100.0%2026-03-13
2026-09-21FINISHED100.0%2026-03-13
2026-09-22FINISHED100.0%2026-03-13
2026-09-23FINISHED100.0%2026-03-13
2026-09-24FINISHED100.0%2026-03-13
2026-09-25FINISHED100.0%2026-03-13
2026-09-26FINISHED100.0%2026-03-13
2026-09-27FINISHED100.0%2026-03-13
2026-09-28FINISHED100.0%2026-03-13
2026-09-29FINISHED100.0%2026-03-13
2026-09-30FINISHED100.0%2026-03-13
2026-10-01FINISHED100.0%2026-03-13
2026-10-02FINISHED100.0%2026-03-13
2026-10-03FINISHED100.0%2026-03-13
2026-10-04FINISHED100.0%2026-03-13
2026-10-05FINISHED100.0%2026-03-13
2026-10-06FINISHED100.0%2026-03-13
2026-10-07FINISHED100.0%2026-03-13
2026-10-08FINISHED100.0%2026-03-13
2026-10-09FINISHED100.0%2026-03-13
2026-10-10FINISHED100.0%2026-03-13
2026-10-11FINISHED100.0%2026-03-13
2026-10-12FINISHED100.0%2026-03-13
2026-10-13FINISHED100.0%2026-03-13
2026-10-14FINISHED100.0%2026-03-13
2026-10-15FINISHED100.0%2026-03-13
2026-10-16FINISHED100.0%2026-03-13
2026-10-17FINISHED100.0%2026-03-13
2026-10-18FINISHED100.0%2026-03-13
2026-10-19FINISHED100.0%2026-03-13
2026-10-20FINISHED100.0%2026-03-13
2026-10-21FINISHED100.0%2026-03-13
2026-10-22FINISHED100.0%2026-03-13
2026-10-23FINISHED100.0%2026-03-13
2026-10-24FINISHED100.0%2026-03-13
2026-10-25FINISHED100.0%2026-03-13
2026-10-26FINISHED100.0%2026-03-13
2026-10-27FINISHED100.0%2026-03-13
2026-10-28FINISHED100.0%2026-03-13
2026-10-29FINISHED100.0%2026-03-13
2026-10-30FINISHED100.0%2026-03-13
2026-10-31FINISHED100.0%2026-03-13
2026-11-01FINISHED100.0%2026-03-13
2026-11-02FINISHED100.0%2026-03-13
2026-11-03FINISHED100.0%2026-03-13
2026-11-04FINISHED100.0%2026-03-13
2026-11-05FINISHED100.0%2026-03-13
2026-11-06FINISHED100.0%2026-03-13
2026-11-07FINISHED100.0%2026-03-13
2026-11-08FINISHED100.0%2026-03-13
2026-11-09FINISHED100.0%2026-03-13
2026-11-10FINISHED100.0%2026-03-13
2026-11-11FINISHED100.0%2026-03-13
2026-11-12FINISHED100.0%2026-03-13
2026-11-13FINISHED100.0%2026-03-13
2026-11-14FINISHED100.0%2026-03-13
2026-11-15FINISHED100.0%2026-03-13
2026-11-16FINISHED100.0%2026-03-13
2026-11-17FINISHED100.0%2026-03-13
2026-11-18FINISHED100.0%2026-03-13
2026-11-19FINISHED100.0%2026-03-13
2026-11-20FINISHED100.0%2026-03-13
2026-11-21FINISHED100.0%2026-03-13
2026-11-22FINISHED100.0%2026-03-13
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.
Track The Valley - Elora