Home / Projects / Mudon Al Ranim 4
Latest DLD inspection photo of Mudon Al Ranim 4
Latest inspection · 2026-01-15 · DLD inspection
Planned handover2026-01-19
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2023-03-01
in the DLD registry
Today
100.0%
last inspected 2026-01-09
Pace forecast
Day 7 of 7
unlocks as daily tracking accrues
Planned handover
2026-01-19
developer's official date

Investor snapshot — estimated yield

5.3%estimated gross rental yield

1,750/sqft median sale price (this project)

93/sqft/yr median rent in Al Hebiah Sixth

Estimate: area-wide median rent ÷ this project’s median sale price, from Dubai Land Department records. Actual rent varies by unit, floor and finish.

How Mudon Al Ranim 4 compares

Similar off-plan projects in Al Hebiah Sixth — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about Mudon Al Ranim 4

Considering buying in Mudon Al Ranim 4? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Watch it rise — one frame per DLD inspection

Mudon Al Ranim 4 on 2023-01-11
2023-01-11 · 0.0% complete
1 / 9

Building & unit mix — from DLD project records

Floors
134
Total units
Buildings
UsageUnit typeUnits
Residential3 B/R76
Residential4 B/R58

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Real sale prices 45 registered DLD sales since 2026-01-08

AED 1,750/sqft
Median sale price
45
Registered sales
45
Sales, last 12 months
Unit typeSalesMedian AED/sqftMedian price
3 B/R251,823AED 3.5M
4 B/R201,550AED 4.6M

Source: DLD registered sale transactions for this project.

Prices by unit size — vs the Al Hebiah Sixth average

BedsUnits soldSize rangeMedian priceAED/sqftArea avgPremium vs area
3 B/R251,8081,975 sqftAED 3.5M1,8231,8250%
4 B/R202,6003,886 sqftAED 4.6M1,5501,491+4%

Median AED/sqft of DLD-registered sales in this project vs all sales in Al Hebiah Sixth for the same unit type. “Premium vs area” is how much more (or less) buyers pay here than the neighbourhood average.

Sale price history 227 sales, median AED/sqft by year

+54% median price growth from 2023 to 2026 · 84% of sales were off-plan

YearMedian AED/sqftSalesYear-on-yearSince launch
2023launch1,136133
20241,25727+11%+11%
20251,49328+19%+31%
20261,75139+17%+54%

Median AED/sqft of DLD-registered sales each year (years with 3+ sales); the earliest year on record approximates launch pricing. “Year-on-year” compares each year to the one before it, “since launch” to the first year. Source: Dubai Land Department transaction records.

Available layouts — check current availability & price

Layouts registered in Mudon Al Ranim 4, grouped by size. We’ll confirm current availability, floor and price with a RERA-licensed agent — we don’t hold live developer inventory, so these are representative configurations, not a live unit list.

BedsSizeTypical priceAED/sqftRegistered
3 B/R1,808 sqftAED 4.3M2,3501
3 B/R1,829 sqftAED 3.3M1,7765
3 B/R1,849 sqftAED 3.3M1,8086
3 B/R1,872 sqftAED 3.7M1,9832
3 B/R1,898 sqftAED 3.8M1,9853
3 B/R1,918 sqftAED 3.3M1,7332
3 B/R1,948 sqftAED 3.5M1,7984
3 B/R1,970 sqftAED 3.9M1,9552
4 B/R2,600 sqftAED 4.5M1,7501
4 B/R2,685 sqftAED 5.2M1,9232
4 B/R2,781 sqftAED 4.3M1,5641
4 B/R2,793 sqftAED 4.3M1,5391
4 B/R2,827 sqftAED 4.5M1,5914
4 B/R2,841 sqftAED 4.2M1,4781

Recent registered sales — individual DLD transactions, newest first

DateBedsSizePriceAED/sqftType
2026-09-044 B/R2,685 sqftAED 5.4M2,021Resale
2026-08-274 B/R3,337 sqftAED 5.3M1,588Resale
2026-08-274 B/R3,590 sqftAED 4.9M1,358Resale
2026-08-253 B/R1,953 sqftAED 3.4M1,741Resale
2026-08-144 B/R3,886 sqftAED 4.9M1,261Resale
2026-08-133 B/R1,878 sqftAED 3.7M1,957Resale
2026-08-034 B/R2,818 sqftAED 4.1M1,455Resale
2026-08-033 B/R1,848 sqftAED 3.4M1,812Resale
2026-07-073 B/R1,829 sqftAED 3.3M1,804Resale
2026-07-033 B/R1,924 sqftAED 3.3M1,716Resale
2026-07-023 B/R1,965 sqftAED 4.1M2,087Resale
2026-06-264 B/R2,836 sqftAED 5.0M1,763Resale
2026-06-224 B/R2,841 sqftAED 4.2M1,478Resale
2026-06-193 B/R1,814 sqftAED 3.2M1,747Resale
2026-06-193 B/R1,943 sqftAED 3.3M1,698Resale
2026-06-184 B/R2,793 sqftAED 4.3M1,539Resale
2026-06-183 B/R1,940 sqftAED 3.6M1,856Resale
2026-06-173 B/R1,904 sqftAED 3.5M1,864Resale
2026-06-163 B/R1,961 sqftAED 4.2M2,117Resale
2026-06-123 B/R1,858 sqftAED 3.0M1,588Resale
2026-06-094 B/R2,781 sqftAED 4.3M1,564Resale
2026-06-083 B/R1,813 sqftAED 3.2M1,752Resale
2026-06-054 B/R2,600 sqftAED 4.5M1,750Resale
2026-06-053 B/R1,913 sqftAED 3.4M1,751Resale
2026-05-223 B/R1,844 sqftAED 3.2M1,735Resale
2026-05-084 B/R3,319 sqftAED 4.3M1,296Resale
2026-05-073 B/R1,834 sqftAED 3.5M1,908Resale
2026-04-303 B/R1,975 sqftAED 3.6M1,823Resale
2026-04-244 B/R3,504 sqftAED 4.6M1,306Resale
2026-04-224 B/R3,358 sqftAED 5.5M1,638Resale
2026-04-074 B/R2,819 sqftAED 4.4M1,561Resale
2026-04-063 B/R1,848 sqftAED 3.3M1,803Resale
2026-04-023 B/R1,866 sqftAED 3.8M2,009Resale
2026-04-023 B/R1,853 sqftAED 3.7M2,010Resale
2026-04-024 B/R3,446 sqftAED 4.8M1,407Resale
2026-04-013 B/R1,898 sqftAED 4.3M2,239Resale
2026-03-253 B/R1,889 sqftAED 3.8M1,985Resale
2026-03-104 B/R2,874 sqftAED 4.8M1,688Resale
2026-03-093 B/R1,808 sqftAED 4.3M2,350Resale
2026-03-034 B/R3,219 sqftAED 4.5M1,398Resale

Source: DLD registered sale transactions. Floor and unit numbers aren’t published in the public transaction feed, so they’re not shown.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
MDN REAL ESTATE L.L.C
Area
Al Hebiah Sixth
Master project
Project type
Normal
Start date
2023-03-01
Planned handover
2026-01-19
Last inspection
2026-01-09
Project value
AED 116.3M
Units
0
Villas
134
Buildings
0
DLD project number
2549

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
2549
Registered with DLD
2023-01-19
Regulator
Dubai Development Authority (DDA)
Escrow account no.
4031224784662009

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Al Hebiah Sixth · See every project on the construction map →

Mudon Al Ranim 4: frequently asked questions — answers update daily from registry data

When will Mudon Al Ranim 4 be handed over?
The developer's planned handover for Mudon Al Ranim 4 is 2026-01-19; construction is currently 100% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on Mudon Al Ranim 4?
Mudon Al Ranim 4 is 100.0% complete according to the Dubai Land Department's inspection of 2026-01-09.
Who is the developer of Mudon Al Ranim 4, and do they deliver on time?
Mudon Al Ranim 4 is developed by MDN REAL ESTATE L.L.C.
What are real sale prices in Mudon Al Ranim 4?
Registered DLD sales in Mudon Al Ranim 4 show a median of AED 1,750/sqft across 45 transactions since 2026-01-08. These are actual registered sales, not asking prices — the full breakdown is on this page.
Where is Mudon Al Ranim 4 located?
Mudon Al Ranim 4 is located in Al Hebiah Sixth, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Mudon Al Ranim 4?
Mudon Al Ranim 4 comprises 134 villas (normal), per the DLD registry.
Can I see real construction photos of Mudon Al Ranim 4?
Yes — this page carries 70 official construction photos taken during Dubai Land Department inspections, newest from 2026-01-15, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in Mudon Al Ranim 4?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for Mudon Al Ranim 4 go?
Only into the project's DLD-registered escrow account (no. 4031224784662009). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on Mudon Al Ranim 4?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Mudon Al Ranim 4's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04FINISHED100.0%2026-01-19
2026-08-05FINISHED100.0%2026-01-19
2026-08-06FINISHED100.0%2026-01-19
2026-08-08FINISHED100.0%2026-01-19
2026-08-09FINISHED100.0%2026-01-19
2026-08-10FINISHED100.0%2026-01-19
2026-08-11FINISHED100.0%2026-01-19
2026-08-12FINISHED100.0%2026-01-19
2026-08-13FINISHED100.0%2026-01-19
2026-08-14FINISHED100.0%2026-01-19
2026-08-15FINISHED100.0%2026-01-19
2026-08-16FINISHED100.0%2026-01-19
2026-08-17FINISHED100.0%2026-01-19
2026-08-18FINISHED100.0%2026-01-19
2026-08-19FINISHED100.0%2026-01-19
2026-08-20FINISHED100.0%2026-01-19
2026-08-21FINISHED100.0%2026-01-19
2026-08-22FINISHED100.0%2026-01-19
2026-08-23FINISHED100.0%2026-01-19
2026-08-24FINISHED100.0%2026-01-19
2026-08-25FINISHED100.0%2026-01-19
2026-08-26FINISHED100.0%2026-01-19
2026-08-27FINISHED100.0%2026-01-19
2026-08-28FINISHED100.0%2026-01-19
2026-08-29FINISHED100.0%2026-01-19
2026-08-30FINISHED100.0%2026-01-19
2026-08-31FINISHED100.0%2026-01-19
2026-09-01FINISHED100.0%2026-01-19
2026-09-02FINISHED100.0%2026-01-19
2026-09-03FINISHED100.0%2026-01-19
2026-09-04FINISHED100.0%2026-01-19
2026-09-05FINISHED100.0%2026-01-19
2026-09-06FINISHED100.0%2026-01-19
2026-09-07FINISHED100.0%2026-01-19
2026-09-08FINISHED100.0%2026-01-19
2026-09-09FINISHED100.0%2026-01-19
2026-09-10FINISHED100.0%2026-01-19
2026-09-11FINISHED100.0%2026-01-19
2026-09-12FINISHED100.0%2026-01-19
2026-09-13FINISHED100.0%2026-01-19
2026-09-14FINISHED100.0%2026-01-19
2026-09-15FINISHED100.0%2026-01-19
2026-09-16FINISHED100.0%2026-01-19
2026-09-17FINISHED100.0%2026-01-19
2026-09-18FINISHED100.0%2026-01-19
2026-09-19FINISHED100.0%2026-01-19
2026-09-20FINISHED100.0%2026-01-19