Home / Projects / California 2 by SD
ACTIVE▲ +19.1% this week

California 2 by SD

SD كاليفورنيا 2 بواسطة
Latest DLD inspection photo of California 2 by SD
Latest inspection · 2026-09-17 · DLD inspection
Planned handover2026-10-31
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2024-04-30
in the DLD registry
Today
33.7%
last inspected 2026-09-09
At the current pace
Planned handover
2026-10-31
developer's official date

How California 2 by SD compares

Similar off-plan projects in Jabal Ali First — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about California 2 by SD

Considering buying in California 2 by SD? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Watch it rise — one frame per DLD inspection

California 2 by SD on 2024-02-20
2024-02-20 · 0.0% complete
1 / 6

Building & unit mix — from DLD project records

11
Floors
155
Total units
1
Building
UsageUnit typeUnits
ResidentialStudio52
Residential1 B/R69
Residential2 B/R34

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Sale price history 157 sales, median AED/sqft by year

-10% median price change from 2024 to 2025 · 99% of sales were off-plan

YearMedian AED/sqftSalesYear-on-yearSince launch
2024launch1,370146
20251,2369-10%-10%

Median AED/sqft of DLD-registered sales each year (years with 3+ sales); the earliest year on record approximates launch pricing. “Year-on-year” compares each year to the one before it, “since launch” to the first year. Source: Dubai Land Department transaction records.

Recent registered sales — individual DLD transactions, newest first

DateBedsSizePriceAED/sqftType
2026-09-09Studio408 sqftAED 769,8921,887Off-plan

Source: DLD registered sale transactions. Floor and unit numbers aren’t published in the public transaction feed, so they’re not shown.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
SAMANA STAR REAL ESTATE DEVELOPMENT L.L.C
Area
Jabal Ali First
Master project
Project type
Normal
Start date
2024-04-30
Planned handover
2026-10-31
Last inspection
2026-09-09
Project value
AED 43.0M
Units
155
Villas
0
Buildings
0
DLD project number
2883

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
2883
Registered with DLD
2024-04-17
Regulator
Trakhees
Escrow account no.
1008898486

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Jabal Ali First · See every project on the construction map →

California 2 by SD: frequently asked questions — answers update daily from registry data

When will California 2 by SD be handed over?
The developer's planned handover for California 2 by SD is 2026-10-31; construction is currently 34% complete. At the observed construction pace, our independent forecast is 2027-03-01.
How far along is construction on California 2 by SD?
California 2 by SD is 33.7% complete according to the Dubai Land Department's inspection of 2026-09-09. Progress moved up 19.1 percentage points at the latest inspection.
Is California 2 by SD delayed?
As of today, California 2 by SD has not passed its planned handover date of 2026-10-31. We compare the official date against the calendar daily and record every change on this page.
Who is the developer of California 2 by SD, and do they deliver on time?
California 2 by SD is developed by SAMANA STAR REAL ESTATE DEVELOPMENT L.L.C. On our Developer Reliability Index they score 92/100 (A On schedule), based on how much of their active portfolio is past its planned handover in the official registry.
Where is California 2 by SD located?
California 2 by SD is located in Jabal Ali First, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in California 2 by SD?
California 2 by SD comprises 155 units (normal), per the DLD registry.
Can I see real construction photos of California 2 by SD?
Yes — this page carries 25 official construction photos taken during Dubai Land Department inspections, newest from 2026-09-17, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in California 2 by SD?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for California 2 by SD go?
Only into the project's DLD-registered escrow account (no. 1008898486). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on California 2 by SD?
Use the free Track this project form on this page. We check the official registry every day and email you the moment California 2 by SD's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE14.6%2026-10-31
2026-08-05ACTIVE14.6%2026-10-31
2026-08-06ACTIVE14.6%2026-10-31
2026-08-08ACTIVE14.6%2026-10-31
2026-08-09ACTIVE14.6%2026-10-31
2026-08-10ACTIVE14.6%2026-10-31
2026-08-11ACTIVE14.6%2026-10-31
2026-08-12ACTIVE14.6%2026-10-31
2026-08-13ACTIVE14.6%2026-10-31
2026-08-14ACTIVE14.6%2026-10-31
2026-08-15ACTIVE14.6%2026-10-31
2026-08-16ACTIVE14.6%2026-10-31
2026-08-17ACTIVE14.6%2026-10-31
2026-08-18ACTIVE14.6%2026-10-31
2026-08-19ACTIVE14.6%2026-10-31
2026-08-20ACTIVE14.6%2026-10-31
2026-08-21ACTIVE14.6%2026-10-31
2026-08-22ACTIVE14.6%2026-10-31
2026-08-23ACTIVE14.6%2026-10-31
2026-08-24ACTIVE14.6%2026-10-31
2026-08-25ACTIVE14.6%2026-10-31
2026-08-26ACTIVE14.6%2026-10-31
2026-08-27ACTIVE14.6%2026-10-31
2026-08-28ACTIVE14.6%2026-10-31
2026-08-29ACTIVE14.6%2026-10-31
2026-08-30ACTIVE14.6%2026-10-31
2026-08-31ACTIVE14.6%2026-10-31
2026-09-01ACTIVE14.6%2026-10-31
2026-09-02ACTIVE14.6%2026-10-31
2026-09-03ACTIVE14.6%2026-10-31
2026-09-04ACTIVE14.6%2026-10-31
2026-09-05ACTIVE14.6%2026-10-31
2026-09-06ACTIVE14.6%2026-10-31
2026-09-07ACTIVE14.6%2026-10-31
2026-09-08ACTIVE14.6%2026-10-31
2026-09-09ACTIVE14.6%2026-10-31
2026-09-10ACTIVE14.6%2026-10-31
2026-09-11ACTIVE14.6%2026-10-31
2026-09-12ACTIVE14.6%2026-10-31
2026-09-13ACTIVE14.6%2026-10-31
2026-09-14ACTIVE14.6%2026-10-31
2026-09-15ACTIVE14.6%2026-10-31
2026-09-16ACTIVE14.6%2026-10-31
2026-09-17ACTIVE14.6%2026-10-31
2026-09-18ACTIVE14.6%2026-10-31
2026-09-19ACTIVE33.7%2026-10-31
2026-09-20ACTIVE33.7%2026-10-31

Change events

DetectedEventChange
2026-09-19PROGRESS14.6133.67
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.
Track California 2 by SD