15%complete
Planned handover2028-07-04
SourceDLD · daily
The road to keys — registry facts, our forecast
Registered start
2026-01-01
in the DLD registry
Today
15.3%
last inspected 2026-07-08
Pace forecast
Day 2 of 7
unlocks as daily tracking accrues
Planned handover
2028-07-04
developer's official date
Track this project
Get an email the moment DLD reports a change — construction progress, a status change, or a handover date that moves.
Watch it rise — one frame per DLD inspection

2024-08-27 · 0.0% complete
1 / 5
Construction photos — official DLD inspection uploads, newest first
Project facts
Developer
AURORA SPV 1 L.L.C
Area
Wadi Al Safa 5
Master project
—
Project type
Normal
Start date
2026-01-01
Planned handover
2028-07-04
Last inspection
2026-07-08
Project value
AED 65.1M
Units
59
Villas
0
Buildings
0
DLD project number
3189
Verdes by Haven 2: frequently asked questions — answers update daily from registry data
When will Verdes by Haven 2 be handed over?
The developer's planned handover for Verdes by Haven 2 is 2028-07-04; construction is currently 15% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on Verdes by Haven 2?
Verdes by Haven 2 is 15.3% complete according to the Dubai Land Department's inspection of 2026-07-08.
Is Verdes by Haven 2 delayed?
As of today, Verdes by Haven 2 has not passed its planned handover date of 2028-07-04. We compare the official date against the calendar daily and record every change on this page.
Who is the developer of Verdes by Haven 2, and do they deliver on time?
Verdes by Haven 2 is developed by AURORA SPV 1 L.L.C. On our Developer Reliability Index they score 90/100 (A — On schedule), based on how much of their active portfolio is past its planned handover in the official registry.
Where is Verdes by Haven 2 located?
Verdes by Haven 2 is located in Wadi Al Safa 5, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Verdes by Haven 2?
Verdes by Haven 2 comprises 59 units (normal), per the DLD registry.
Can I see real construction photos of Verdes by Haven 2?
Yes — this page carries 16 official construction photos taken during Dubai Land Department inspections, newest from 2026-07-23, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in Verdes by Haven 2?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
How do I get alerts when something changes on Verdes by Haven 2?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Verdes by Haven 2's progress, status, or planned handover date changes.
Progress history — one row per official DLD snapshot
| Snapshot date | Status | Complete | Planned handover |
|---|---|---|---|
| 2026-08-04 | ACTIVE | 15.3% | 2028-07-04 |
| 2026-08-05 | ACTIVE | 15.3% | 2028-07-04 |
| 2026-08-06 | ACTIVE | 15.3% | 2028-07-04 |
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.
Track Verdes by Haven 2