Home / Projects / Al Haseen Residence 4
Latest DLD inspection photo of Al Haseen Residence 4
Latest inspection · 2026-07-14 · DLD inspection
Planned handover2026-12-30
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2025-06-29
in the DLD registry
Today
11.8%
last inspected 2026-07-09
Pace forecast
Day 7 of 7
unlocks as daily tracking accrues
Planned handover
2026-12-30
developer's official date

How Al Haseen Residence 4 compares

Similar off-plan projects in Saih Shuaib 2 — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about Al Haseen Residence 4

Considering buying in Al Haseen Residence 4? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Watch it rise — one frame per DLD inspection

Al Haseen Residence 4 on 2025-02-17
2025-02-17 · 0.0% complete
1 / 3

Building & unit mix — from DLD project records

8
Floors
248
Total units
1
Building
UsageUnit typeUnits
ResidentialStudio238
Residential1 B/R5
Residential2 B/R5

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Real sale prices 77 registered DLD sales since 2026-01-02

AED 1,455/sqft
Median sale price
77
Registered sales
77
Sales, last 12 months
Unit typeSalesMedian AED/sqftMedian price
Studio771,455AED 566,626

Source: DLD registered sale transactions for this project.

Prices by unit size — vs the Saih Shuaib 2 average

BedsUnits soldSize rangeMedian priceAED/sqftArea avgPremium vs area
Studio77292541 sqftAED 566,6261,455

Median AED/sqft of DLD-registered sales in this project vs all sales in Saih Shuaib 2 for the same unit type. “Premium vs area” is how much more (or less) buyers pay here than the neighbourhood average.

Sale price history 138 sales, median AED/sqft by year

+0% median price growth from 2025 to 2026 · 99% of sales were off-plan

YearMedian AED/sqftSalesYear-on-yearSince launch
2025launch1,45066
20261,45570+0%+0%

Median AED/sqft of DLD-registered sales each year (years with 3+ sales); the earliest year on record approximates launch pricing. “Year-on-year” compares each year to the one before it, “since launch” to the first year. Source: Dubai Land Department transaction records.

Available layouts — check current availability & price

Layouts registered in Al Haseen Residence 4, grouped by size. We’ll confirm current availability, floor and price with a RERA-licensed agent — we don’t hold live developer inventory, so these are representative configurations, not a live unit list.

BedsSizeTypical priceAED/sqftRegistered
Studio292 sqftAED 393K1,3462
Studio385 sqftAED 562K1,47070
Studio394 sqftAED 573K1,4703
Studio428 sqftAED 597K1,3951
Studio541 sqftAED 748K1,3831

Recent registered sales — individual DLD transactions, newest first

DateBedsSizePriceAED/sqftType
2026-09-11Studio386 sqftAED 579,4801,500Off-plan
2026-09-11Studio385 sqftAED 600,0841,557Off-plan
2026-09-08Studio381 sqftAED 460,4341,207Off-plan
2026-09-08Studio292 sqftAED 385,1891,320Off-plan
2026-09-08Studio385 sqftAED 465,0001,206Off-plan
2026-08-17Studio385 sqftAED 605,4791,573Off-plan
2026-08-17Studio385 sqftAED 465,0001,206Off-plan
2026-08-14Studio385 sqftAED 574,3351,490Off-plan
2026-07-17Studio385 sqftAED 642,1761,666Off-plan
2026-07-17Studio381 sqftAED 533,1621,400Off-plan
2026-07-17Studio541 sqftAED 748,3591,383Off-plan
2026-06-18Studio384 sqftAED 448,2391,169Off-plan
2026-06-18Studio381 sqftAED 445,0951,169Off-plan
2026-06-18Studio381 sqftAED 445,0951,169Off-plan
2026-06-18Studio381 sqftAED 445,0951,169Off-plan
2026-06-18Studio381 sqftAED 445,0951,169Off-plan
2026-06-18Studio381 sqftAED 445,0951,169Off-plan
2026-06-18Studio379 sqftAED 442,9561,169Off-plan
2026-06-18Studio366 sqftAED 427,2251,169Off-plan
2026-06-18Studio366 sqftAED 427,2251,169Off-plan
2026-06-18Studio366 sqftAED 427,2251,169Off-plan
2026-06-11Studio379 sqftAED 606,4001,600Off-plan
2026-06-11Studio385 sqftAED 577,3801,500Off-plan
2026-06-11Studio385 sqftAED 615,8721,600Off-plan
2026-06-11Studio386 sqftAED 480,9681,245Off-plan
2026-05-19Studio385 sqftAED 591,2371,536Off-plan
2026-05-12Studio386 sqftAED 560,1641,450Off-plan
2026-05-12Studio381 sqftAED 515,1121,353Off-plan
2026-05-12Studio381 sqftAED 515,1121,353Off-plan
2026-05-11Studio394 sqftAED 573,2121,455Off-plan
2026-05-06Studio379 sqftAED 606,4001,600Off-plan
2026-04-21Studio390 sqftAED 573,4181,470Off-plan
2026-03-30Studio379 sqftAED 447,7891,182Off-plan
2026-03-13Studio428 sqftAED 596,5721,395Off-plan
2026-02-28Studio385 sqftAED 526,1531,365Off-plan
2026-02-26Studio383 sqftAED 594,5561,552Off-plan
2026-02-26Studio379 sqftAED 557,1301,470Off-plan
2026-02-24Studio385 sqftAED 577,3801,500Off-plan
2026-02-20Studio292 sqftAED 400,0721,371Off-plan
2026-02-19Studio381 sqftAED 603,2351,584Off-plan

Source: DLD registered sale transactions. Floor and unit numbers aren’t published in the public transaction feed, so they’re not shown.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
DUGASTA PROPERTIES DEVELOPMENT L.L.C
Area
Saih Shuaib 2
Master project
Project type
Normal
Start date
2025-06-29
Planned handover
2026-12-30
Last inspection
2026-07-09
Project value
AED 50.0M
Units
248
Villas
0
Buildings
0
DLD project number
3562

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
3562
Registered with DLD
2025-04-04
Regulator
Dubai Development Authority (DDA)
Escrow account no.
0205771071202

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Saih Shuaib 2 · See every project on the construction map →

Al Haseen Residence 4: frequently asked questions — answers update daily from registry data

When will Al Haseen Residence 4 be handed over?
The developer's planned handover for Al Haseen Residence 4 is 2026-12-30; construction is currently 12% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on Al Haseen Residence 4?
Al Haseen Residence 4 is 11.8% complete according to the Dubai Land Department's inspection of 2026-07-09.
Is Al Haseen Residence 4 delayed?
As of today, Al Haseen Residence 4 has not passed its planned handover date of 2026-12-30. We compare the official date against the calendar daily and record every change on this page.
Who is the developer of Al Haseen Residence 4, and do they deliver on time?
Al Haseen Residence 4 is developed by DUGASTA PROPERTIES DEVELOPMENT L.L.C. On our Developer Reliability Index they score 92/100 (A On schedule), based on how much of their active portfolio is past its planned handover in the official registry.
What are real sale prices in Al Haseen Residence 4?
Registered DLD sales in Al Haseen Residence 4 show a median of AED 1,455/sqft across 77 transactions since 2026-01-02. These are actual registered sales, not asking prices — the full breakdown is on this page.
Where is Al Haseen Residence 4 located?
Al Haseen Residence 4 is located in Saih Shuaib 2, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Al Haseen Residence 4?
Al Haseen Residence 4 comprises 248 units (normal), per the DLD registry.
Can I see real construction photos of Al Haseen Residence 4?
Yes — this page carries 11 official construction photos taken during Dubai Land Department inspections, newest from 2026-07-14, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in Al Haseen Residence 4?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for Al Haseen Residence 4 go?
Only into the project's DLD-registered escrow account (no. 0205771071202). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on Al Haseen Residence 4?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Al Haseen Residence 4's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE11.8%2026-12-30
2026-08-05ACTIVE11.8%2026-12-30
2026-08-06ACTIVE11.8%2026-12-30
2026-08-08ACTIVE11.8%2026-12-30
2026-08-09ACTIVE11.8%2026-12-30
2026-08-10ACTIVE11.8%2026-12-30
2026-08-11ACTIVE11.8%2026-12-30
2026-08-12ACTIVE11.8%2026-12-30
2026-08-13ACTIVE11.8%2026-12-30
2026-08-14ACTIVE11.8%2026-12-30
2026-08-15ACTIVE11.8%2026-12-30
2026-08-16ACTIVE11.8%2026-12-30
2026-08-17ACTIVE11.8%2026-12-30
2026-08-18ACTIVE11.8%2026-12-30
2026-08-19ACTIVE11.8%2026-12-30
2026-08-20ACTIVE11.8%2026-12-30
2026-08-21ACTIVE11.8%2026-12-30
2026-08-22ACTIVE11.8%2026-12-30
2026-08-23ACTIVE11.8%2026-12-30
2026-08-24ACTIVE11.8%2026-12-30
2026-08-25ACTIVE11.8%2026-12-30
2026-08-26ACTIVE11.8%2026-12-30
2026-08-27ACTIVE11.8%2026-12-30
2026-08-28ACTIVE11.8%2026-12-30
2026-08-29ACTIVE11.8%2026-12-30
2026-08-30ACTIVE11.8%2026-12-30
2026-08-31ACTIVE11.8%2026-12-30
2026-09-01ACTIVE11.8%2026-12-30
2026-09-02ACTIVE11.8%2026-12-30
2026-09-03ACTIVE11.8%2026-12-30
2026-09-04ACTIVE11.8%2026-12-30
2026-09-05ACTIVE11.8%2026-12-30
2026-09-06ACTIVE11.8%2026-12-30
2026-09-07ACTIVE11.8%2026-12-30
2026-09-08ACTIVE11.8%2026-12-30
2026-09-09ACTIVE11.8%2026-12-30
2026-09-10ACTIVE11.8%2026-12-30
2026-09-11ACTIVE11.8%2026-12-30
2026-09-12ACTIVE11.8%2026-12-30
2026-09-13ACTIVE11.8%2026-12-30
2026-09-14ACTIVE11.8%2026-12-30
2026-09-15ACTIVE11.8%2026-12-30
2026-09-16ACTIVE11.8%2026-12-30
2026-09-17ACTIVE11.8%2026-12-30
2026-09-18ACTIVE11.8%2026-12-30
2026-09-19ACTIVE11.8%2026-12-30
2026-09-20ACTIVE11.8%2026-12-30
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.
Track Al Haseen Residence 4