Binghatti Moonlight

بن غاطي مونلايت
Latest DLD inspection photo of Binghatti Moonlight
Latest inspection · 2026-06-29 · DLD inspection
Planned handover2026-06-15
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2025-04-15
in the DLD registry
Today
19.2%
last inspected 2026-04-28
Pace forecast
Day 7 of 7
unlocks as daily tracking accrues
Planned handover
2026-06-15
97 days overdue — developer's official date

Investor snapshot — estimated yield

4.2%estimated gross rental yield

1,993/sqft median sale price (this project)

84/sqft/yr median rent in Al Jadaf

Estimate: area-wide median rent ÷ this project’s median sale price, from Dubai Land Department records. Actual rent varies by unit, floor and finish.

How Binghatti Moonlight compares

Similar off-plan projects in Al Jadaf — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about Binghatti Moonlight

Considering buying in Binghatti Moonlight? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Building & unit mix — from DLD project records

32
Floors
286
Total units
1
Building
UsageUnit typeUnits
CommercialUnspecified50
Residential1 B/R126
Residential2 B/R106
Residential3 B/R4

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Real sale prices 36 registered DLD sales since 2026-01-07

AED 1,993/sqft
Median sale price
36
Registered sales
36
Sales, last 12 months
Unit typeSalesMedian AED/sqftMedian price
2 B/R192,034AED 1.9M
1 B/R131,918AED 1.5M
NA42,907AED 2.6M

Source: DLD registered sale transactions for this project.

Prices by unit size — vs the Al Jadaf average

BedsUnits soldSize rangeMedian priceAED/sqftArea avgPremium vs area
1 B/R13746824 sqftAED 1.5M1,9181,832+5%
2 B/R199341,186 sqftAED 1.9M2,0341,614+26%
NA46021,098 sqftAED 2.6M2,907

Median AED/sqft of DLD-registered sales in this project vs all sales in Al Jadaf for the same unit type. “Premium vs area” is how much more (or less) buyers pay here than the neighbourhood average.

Sale price history 250 sales, median AED/sqft by year

+3% median price growth from 2025 to 2026 · 99% of sales were off-plan

YearMedian AED/sqftSalesYear-on-yearSince launch
2025launch1,934218
20261,99931+3%+3%

Median AED/sqft of DLD-registered sales each year (years with 3+ sales); the earliest year on record approximates launch pricing. “Year-on-year” compares each year to the one before it, “since launch” to the first year. Source: Dubai Land Department transaction records.

Available layouts — check current availability & price

Layouts registered in Binghatti Moonlight, grouped by size. We’ll confirm current availability, floor and price with a RERA-licensed agent — we don’t hold live developer inventory, so these are representative configurations, not a live unit list.

BedsSizeTypical priceAED/sqftRegistered
1 B/R746 sqftAED 1.4M1,9252
1 B/R778 sqftAED 1.5M1,9291
1 B/R810 sqftAED 1.4M1,6683
1 B/R818 sqftAED 1.6M1,9997
2 B/R934 sqftAED 1.9M2,0398
2 B/R1,018 sqftAED 2.0M1,9869
2 B/R1,186 sqftAED 2.2M1,8802
NA602 sqftAED 1.5M2,4991
NA803 sqftAED 2.3M2,9051
NA959 sqftAED 2.8M2,9081
NA1,098 sqftAED 3.8M3,4971

Recent registered sales — individual DLD transactions, newest first

DateBedsSizePriceAED/sqftType
2026-09-182 B/R934 sqftAED 1.9M2,034Off-plan
2026-09-172 B/R1,018 sqftAED 2.0M1,964Off-plan
2026-09-11NA602 sqftAED 1.5M2,499Off-plan
2026-09-021 B/R810 sqftAED 1.3M1,640Off-plan
2026-08-191 B/R746 sqftAED 1.4M1,932Off-plan
2026-07-161 B/R824 sqftAED 1.4M1,639Off-plan
2026-07-161 B/R810 sqftAED 1.4M1,668Off-plan
2026-07-131 B/R824 sqftAED 1.5M1,850Off-plan
2026-06-242 B/R934 sqftAED 1.8M1,873Off-plan
2026-06-191 B/R816 sqftAED 1.5M1,886Off-plan
2026-06-182 B/R1,186 sqftAED 2.2M1,874Off-plan
2026-06-172 B/R1,025 sqftAED 2.0M1,986Off-plan
2026-06-171 B/R818 sqftAED 1.7M2,028Off-plan
2026-06-161 B/R746 sqftAED 1.4M1,918Off-plan
2026-06-102 B/R1,018 sqftAED 2.1M2,075Off-plan
2026-06-02NA803 sqftAED 2.3M2,905Off-plan
2026-05-212 B/R1,025 sqftAED 1.9M1,892Off-plan
2026-05-212 B/R934 sqftAED 1.9M2,036Off-plan
2026-04-162 B/R934 sqftAED 1.9M2,038Off-plan
2026-04-141 B/R804 sqftAED 1.5M1,896Off-plan
2026-04-012 B/R934 sqftAED 1.9M2,046Off-plan
2026-03-23NA959 sqftAED 2.8M2,908Off-plan
2026-03-092 B/R934 sqftAED 1.9M2,064Off-plan
2026-03-041 B/R816 sqftAED 1.6M2,009Off-plan
2026-03-042 B/R1,025 sqftAED 2.0M1,984Off-plan
2026-02-24NA1,098 sqftAED 3.8M3,497Off-plan
2026-02-232 B/R1,018 sqftAED 2.1M2,086Off-plan
2026-02-121 B/R818 sqftAED 1.6M2,010Off-plan
2026-02-092 B/R934 sqftAED 1.9M2,040Off-plan
2026-02-062 B/R934 sqftAED 1.9M2,045Off-plan
2026-02-022 B/R1,025 sqftAED 2.0M1,988Off-plan
2026-01-221 B/R778 sqftAED 1.5M1,929Off-plan
2026-01-132 B/R1,018 sqftAED 2.1M2,055Off-plan
2026-01-081 B/R816 sqftAED 1.6M1,999Off-plan
2026-01-082 B/R1,018 sqftAED 1.9M1,817Off-plan
2026-01-072 B/R1,186 sqftAED 2.2M1,886Off-plan

Source: DLD registered sale transactions. Floor and unit numbers aren’t published in the public transaction feed, so they’re not shown.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
Binghatti Developers FZE
Area
Al Jadaf
Master project
Project type
Normal
Start date
2025-04-15
Planned handover
2026-06-15
Last inspection
2026-04-28
Project value
AED 256.0M
Units
286
Villas
0
Buildings
0
DLD project number
3722

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
3722
Registered with DLD
2025-06-11
Regulator
Dubai Development Authority (DDA)
Escrow account no.
001582194178101

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Al Jadaf · See every project on the construction map →

Binghatti Moonlight: frequently asked questions — answers update daily from registry data

When will Binghatti Moonlight be handed over?
The developer's planned handover for Binghatti Moonlight is 2026-06-15; construction is currently 19% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on Binghatti Moonlight?
Binghatti Moonlight is 19.2% complete according to the Dubai Land Department's inspection of 2026-04-28.
Is Binghatti Moonlight delayed?
Binghatti Moonlight is 97 days past its planned handover of 2026-06-15 and still under construction. Most Dubai off-plan contracts include a grace period (often 6–12 months) beyond the anticipated date — see The Late List for how it compares.
Who is the developer of Binghatti Moonlight, and do they deliver on time?
Binghatti Moonlight is developed by Binghatti Developers FZE. On our Developer Reliability Index they score 66/100 (C Slipping), based on how much of their active portfolio is past its planned handover in the official registry.
What are real sale prices in Binghatti Moonlight?
Registered DLD sales in Binghatti Moonlight show a median of AED 1,993/sqft across 36 transactions since 2026-01-07. These are actual registered sales, not asking prices — the full breakdown is on this page.
Where is Binghatti Moonlight located?
Binghatti Moonlight is located in Al Jadaf, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Binghatti Moonlight?
Binghatti Moonlight comprises 286 units (normal), per the DLD registry.
Can I see real construction photos of Binghatti Moonlight?
Yes — this page carries 9 official construction photos taken during Dubai Land Department inspections, newest from 2026-06-29, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in Binghatti Moonlight?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for Binghatti Moonlight go?
Only into the project's DLD-registered escrow account (no. 001582194178101). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on Binghatti Moonlight?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Binghatti Moonlight's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE19.2%2026-06-15
2026-08-05ACTIVE19.2%2026-06-15
2026-08-06ACTIVE19.2%2026-06-15
2026-08-08ACTIVE19.2%2026-06-15
2026-08-09ACTIVE19.2%2026-06-15
2026-08-10ACTIVE19.2%2026-06-15
2026-08-11ACTIVE19.2%2026-06-15
2026-08-12ACTIVE19.2%2026-06-15
2026-08-13ACTIVE19.2%2026-06-15
2026-08-14ACTIVE19.2%2026-06-15
2026-08-15ACTIVE19.2%2026-06-15
2026-08-16ACTIVE19.2%2026-06-15
2026-08-17ACTIVE19.2%2026-06-15
2026-08-18ACTIVE19.2%2026-06-15
2026-08-19ACTIVE19.2%2026-06-15
2026-08-20ACTIVE19.2%2026-06-15
2026-08-21ACTIVE19.2%2026-06-15
2026-08-22ACTIVE19.2%2026-06-15
2026-08-23ACTIVE19.2%2026-06-15
2026-08-24ACTIVE19.2%2026-06-15
2026-08-25ACTIVE19.2%2026-06-15
2026-08-26ACTIVE19.2%2026-06-15
2026-08-27ACTIVE19.2%2026-06-15
2026-08-28ACTIVE19.2%2026-06-15
2026-08-29ACTIVE19.2%2026-06-15
2026-08-30ACTIVE19.2%2026-06-15
2026-08-31ACTIVE19.2%2026-06-15
2026-09-01ACTIVE19.2%2026-06-15
2026-09-02ACTIVE19.2%2026-06-15
2026-09-03ACTIVE19.2%2026-06-15
2026-09-04ACTIVE19.2%2026-06-15
2026-09-05ACTIVE19.2%2026-06-15
2026-09-06ACTIVE19.2%2026-06-15
2026-09-07ACTIVE19.2%2026-06-15
2026-09-08ACTIVE19.2%2026-06-15
2026-09-09ACTIVE19.2%2026-06-15
2026-09-10ACTIVE19.2%2026-06-15
2026-09-11ACTIVE19.2%2026-06-15
2026-09-12ACTIVE19.2%2026-06-15
2026-09-13ACTIVE19.2%2026-06-15
2026-09-14ACTIVE19.2%2026-06-15
2026-09-15ACTIVE19.2%2026-06-15
2026-09-16ACTIVE19.2%2026-06-15
2026-09-17ACTIVE19.2%2026-06-15
2026-09-18ACTIVE19.2%2026-06-15
2026-09-19ACTIVE19.2%2026-06-15
2026-09-20ACTIVE19.2%2026-06-15
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.
Track Binghatti Moonlight