AVA AT PALM JUMEIRAH BY OMNIYAT

The road to keys — registry facts, our forecast
How AVA AT PALM JUMEIRAH BY OMNIYAT compares
Similar off-plan projects in Palm Jumeirah — compare progress, handover and developer.
Track this project
Get an email the moment DLD reports a change — construction progress, a status change, or a handover date that moves.
One click. Creates your free account — no password, ever.
Talk to a verified agent about AVA AT PALM JUMEIRAH BY OMNIYAT
Considering buying in AVA AT PALM JUMEIRAH BY OMNIYAT? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.
Watch it rise — one frame per DLD inspection
.jpg)
Building & unit mix — from DLD project records
| Usage | Unit type | Units |
|---|---|---|
| Residential | 3 B/R | 5 |
| Residential | 4 B/R | 11 |
| Residential | 5 B/R | 1 |
Source: DLD project register — floors, buildings and the developer's registered unit mix.
Sale price history — 22 sales, median AED/sqft by year
+8% median price growth from 2022 to 2023 · 95% of sales were off-plan
| Year | Median AED/sqft | Sales | Year-on-year | Since launch |
|---|---|---|---|---|
| 2022launch | 6,782 | 9 | — | — |
| 2023 | 7,293 | 6 | +8% | +8% |
| 2025 | 7,385 | 3 | +1% | +9% |
Median AED/sqft of DLD-registered sales each year (years with 3+ sales); the earliest year on record approximates launch pricing. “Year-on-year” compares each year to the one before it, “since launch” to the first year. Source: Dubai Land Department transaction records.
Recent registered sales — individual DLD transactions, newest first
| Date | Beds | Size | Price | AED/sqft | Type |
|---|---|---|---|---|---|
| 2026-02-05 | 4 B/R | 6,719 sqft | AED 38.0M | 5,660 | Off-plan |
| 2026-01-07 | 4 B/R | 7,024 sqft | AED 54.0M | 7,688 | Off-plan |
Source: DLD registered sale transactions. Floor and unit numbers aren’t published in the public transaction feed, so they’re not shown.
Construction photos — official DLD inspection uploads, newest first
Project facts
Registration & escrow — verify before you pay anyone
Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →
Location — official site coordinates from DLD inspection records
Palm Jumeirah · See every project on the construction map →
AVA AT PALM JUMEIRAH BY OMNIYAT: frequently asked questions — answers update daily from registry data
When will AVA AT PALM JUMEIRAH BY OMNIYAT be handed over?
How far along is construction on AVA AT PALM JUMEIRAH BY OMNIYAT?
Is AVA AT PALM JUMEIRAH BY OMNIYAT delayed?
Who is the developer of AVA AT PALM JUMEIRAH BY OMNIYAT, and do they deliver on time?
Where is AVA AT PALM JUMEIRAH BY OMNIYAT located?
How many homes are in AVA AT PALM JUMEIRAH BY OMNIYAT?
Can I see real construction photos of AVA AT PALM JUMEIRAH BY OMNIYAT?
Is my money safe if I buy in AVA AT PALM JUMEIRAH BY OMNIYAT?
Where should payments for AVA AT PALM JUMEIRAH BY OMNIYAT go?
How do I get alerts when something changes on AVA AT PALM JUMEIRAH BY OMNIYAT?
Progress history — one row per official DLD snapshot
| Snapshot date | Status | Complete | Planned handover |
|---|---|---|---|
| 2026-08-04 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-05 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-06 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-08 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-09 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-10 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-11 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-12 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-13 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-14 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-15 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-16 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-17 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-18 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-19 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-20 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-21 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-22 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-23 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-24 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-25 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-26 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-27 | ACTIVE | 91.0% | 2025-12-31 |
| 2026-08-28 | ACTIVE | 91.0% | 2026-06-30 |
| 2026-08-29 | ACTIVE | 91.0% | 2026-06-30 |
| 2026-08-30 | ACTIVE | 91.0% | 2026-06-30 |
| 2026-08-31 | ACTIVE | 91.0% | 2026-06-30 |
| 2026-09-01 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-02 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-03 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-04 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-05 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-06 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-07 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-08 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-09 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-10 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-11 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-12 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-13 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-14 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-15 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-16 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-17 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-18 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-19 | ACTIVE | 95.9% | 2026-06-30 |
| 2026-09-20 | ACTIVE | 95.9% | 2026-06-30 |
Change events
| Detected | Event | Change |
|---|---|---|
| 2026-09-01 | PROGRESS | 91.02 → 95.93 |
| 2026-08-28 | HANDOVER_SLIP | 2025-12-31 → 2026-06-30 |