Latest DLD inspection photo of One Crescent
Latest inspection · 2026-07-28 · DLD inspection
Planned handover2026-03-01
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2023-05-15
in the DLD registry
Today
80.0%
last inspected 2026-07-23
Pace forecast
Day 7 of 7
unlocks as daily tracking accrues
Planned handover
2026-03-01
204 days overdue — developer's official date

How One Crescent compares

Similar off-plan projects in Palm Jumeirah — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about One Crescent

Considering buying in One Crescent? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Watch it rise — one frame per DLD inspection

One Crescent on 2023-01-30
2023-01-30 · 0.0% complete
1 / 9

Building & unit mix — from DLD project records

11
Floors
25
Total units
1
Building
UsageUnit typeUnits
Residential3 B/R14
Residential4 B/R3
Residential5 B/R6
Residential6 B/R2

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Sale price history 26 sales, median AED/sqft by year

YearMedian AED/sqftSalesYear-on-yearSince launch
2023launch3,95719
20243,6474-8%-8%

Median AED/sqft of DLD-registered sales each year (years with 3+ sales); the earliest year on record approximates launch pricing. “Year-on-year” compares each year to the one before it, “since launch” to the first year. Source: Dubai Land Department transaction records.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
A H S PALM DEVELOPMENT L.L.C
Area
Palm Jumeirah
Master project
Project type
Normal
Start date
2023-05-15
Planned handover
2026-03-01
Last inspection
2026-07-23
Project value
AED 176.0M
Units
25
Villas
0
Buildings
0
DLD project number
2567

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
2567
Registered with DLD
2023-03-16
Regulator
Trakhees
Escrow account no.
12711866920002

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Palm Jumeirah · See every project on the construction map →

One Crescent: frequently asked questions — answers update daily from registry data

When will One Crescent be handed over?
The developer's planned handover for One Crescent is 2026-03-01; construction is currently 80% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on One Crescent?
One Crescent is 80.0% complete according to the Dubai Land Department's inspection of 2026-07-23.
Is One Crescent delayed?
One Crescent is 204 days past its planned handover of 2026-03-01 and still under construction. Most Dubai off-plan contracts include a grace period (often 6–12 months) beyond the anticipated date — see The Late List for how it compares.
Who is the developer of One Crescent, and do they deliver on time?
One Crescent is developed by A H S PALM DEVELOPMENT L.L.C. On our Developer Reliability Index they score 68/100 (C Slipping), based on how much of their active portfolio is past its planned handover in the official registry.
Where is One Crescent located?
One Crescent is located in Palm Jumeirah, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in One Crescent?
One Crescent comprises 25 units (normal), per the DLD registry.
Can I see real construction photos of One Crescent?
Yes — this page carries 59 official construction photos taken during Dubai Land Department inspections, newest from 2026-07-28, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in One Crescent?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for One Crescent go?
Only into the project's DLD-registered escrow account (no. 12711866920002). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on One Crescent?
Use the free Track this project form on this page. We check the official registry every day and email you the moment One Crescent's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE80.0%2026-03-01
2026-08-05ACTIVE80.0%2026-03-01
2026-08-06ACTIVE80.0%2026-03-01
2026-08-08ACTIVE80.0%2026-03-01
2026-08-09ACTIVE80.0%2026-03-01
2026-08-10ACTIVE80.0%2026-03-01
2026-08-11ACTIVE80.0%2026-03-01
2026-08-12ACTIVE80.0%2026-03-01
2026-08-13ACTIVE80.0%2026-03-01
2026-08-14ACTIVE80.0%2026-03-01
2026-08-15ACTIVE80.0%2026-03-01
2026-08-16ACTIVE80.0%2026-03-01
2026-08-17ACTIVE80.0%2026-03-01
2026-08-18ACTIVE80.0%2026-03-01
2026-08-19ACTIVE80.0%2026-03-01
2026-08-20ACTIVE80.0%2026-03-01
2026-08-21ACTIVE80.0%2026-03-01
2026-08-22ACTIVE80.0%2026-03-01
2026-08-23ACTIVE80.0%2026-03-01
2026-08-24ACTIVE80.0%2026-03-01
2026-08-25ACTIVE80.0%2026-03-01
2026-08-26ACTIVE80.0%2026-03-01
2026-08-27ACTIVE80.0%2026-03-01
2026-08-28ACTIVE80.0%2026-03-01
2026-08-29ACTIVE80.0%2026-03-01
2026-08-30ACTIVE80.0%2026-03-01
2026-08-31ACTIVE80.0%2026-03-01
2026-09-01ACTIVE80.0%2026-03-01
2026-09-02ACTIVE80.0%2026-03-01
2026-09-03ACTIVE80.0%2026-03-01
2026-09-04ACTIVE80.0%2026-03-01
2026-09-05ACTIVE80.0%2026-03-01
2026-09-06ACTIVE80.0%2026-03-01
2026-09-07ACTIVE80.0%2026-03-01
2026-09-08ACTIVE80.0%2026-03-01
2026-09-09ACTIVE80.0%2026-03-01
2026-09-10ACTIVE80.0%2026-03-01
2026-09-11ACTIVE80.0%2026-03-01
2026-09-12ACTIVE80.0%2026-03-01
2026-09-13ACTIVE80.0%2026-03-01
2026-09-14ACTIVE80.0%2026-03-01
2026-09-15ACTIVE80.0%2026-03-01
2026-09-16ACTIVE80.0%2026-03-01
2026-09-17ACTIVE80.0%2026-03-01
2026-09-18ACTIVE80.0%2026-03-01
2026-09-19ACTIVE80.0%2026-03-01
2026-09-20ACTIVE80.0%2026-03-01
2026-09-21ACTIVE80.0%2026-03-01
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.