Home / Projects / Skyhills III by HRE
ACTIVE

Skyhills III by HRE

من اتش ار اي III سكاي هيلز
Latest DLD inspection photo of Skyhills III by HRE
Latest inspection · 2026-09-01 · DLD inspection
Planned handover2026-06-01
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2024-06-01
in the DLD registry
Today
In construction
75.7% at the 2026-09-01 inspection — DLD's headline figure (235.9%) is invalid
Pace forecast
Day 7 of 7
unlocks as daily tracking accrues
Planned handover
2026-06-01
111 days overdue — developer's official date

Investor snapshot — estimated yield

5.5%estimated gross rental yield

1,598/sqft median sale price (this project)

89/sqft/yr median rent in Al Barsha South Fourth

Estimate: area-wide median rent ÷ this project’s median sale price, from Dubai Land Department records. Actual rent varies by unit, floor and finish.

How Skyhills III by HRE compares

Similar off-plan projects in Al Barsha South Fourth — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about Skyhills III by HRE

Considering buying in Skyhills III by HRE? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Watch it rise — one frame per DLD inspection

Skyhills III by HRE on 2024-07-04
2024-07-04 · 20.3% complete
1 / 7

Building & unit mix — from DLD project records

47
Floors
516
Total units
2
Buildings
UsageUnit typeUnits
CommercialUnspecified12
ResidentialStudio220
Residential1 B/R152
Residential2 B/R129
Residential3 B/R1
Residential4 B/R2

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Real sale prices 48 registered DLD sales since 2026-01-07

AED 1,598/sqft
Median sale price
48
Registered sales
48
Sales, last 12 months
Unit typeSalesMedian AED/sqftMedian price
2 B/R211,543AED 1.7M
1 B/R201,643AED 1.3M
NA42,201AED 10.9M
Studio31,776AED 712,328

Source: DLD registered sale transactions for this project.

Prices by unit size — vs the Al Barsha South Fourth average

BedsUnits soldSize rangeMedian priceAED/sqftArea avgPremium vs area
Studio3347417 sqftAED 712,3281,776
1 B/R206811,341 sqftAED 1.3M1,643
2 B/R211,0381,481 sqftAED 1.7M1,543
NA42,9805,966 sqftAED 10.9M2,201

Median AED/sqft of DLD-registered sales in this project vs all sales in Al Barsha South Fourth for the same unit type. “Premium vs area” is how much more (or less) buyers pay here than the neighbourhood average.

Sale price history 428 sales, median AED/sqft by year

-7% median price change from 2025 to 2026 · 100% of sales were off-plan

YearMedian AED/sqftSalesYear-on-yearSince launch
2025launch1,722380
20261,59446-7%-7%

Median AED/sqft of DLD-registered sales each year (years with 3+ sales); the earliest year on record approximates launch pricing. “Year-on-year” compares each year to the one before it, “since launch” to the first year. Source: Dubai Land Department transaction records.

Available layouts — check current availability & price

Layouts registered in Skyhills III by HRE, grouped by size. We’ll confirm current availability, floor and price with a RERA-licensed agent — we don’t hold live developer inventory, so these are representative configurations, not a live unit list.

BedsSizeTypical priceAED/sqftRegistered
Studio347 sqftAED 700K2,0161
Studio401 sqftAED 712K1,7761
Studio417 sqftAED 729K1,7481
1 B/R681 sqftAED 1.1M1,5812
1 B/R745 sqftAED 1.3M1,6972
1 B/R789 sqftAED 1.3M1,6453
1 B/R820 sqftAED 1.3M1,64311
1 B/R860 sqftAED 1.3M1,5281
1 B/R1,341 sqftAED 1.4M1,0151
2 B/R1,039 sqftAED 1.7M1,5925
2 B/R1,095 sqftAED 1.7M1,5948
2 B/R1,155 sqftAED 1.6M1,4281
2 B/R1,240 sqftAED 1.7M1,4031
2 B/R1,326 sqftAED 1.9M1,4163

Recent registered sales — individual DLD transactions, newest first

DateBedsSizePriceAED/sqftType
2026-08-272 B/R1,095 sqftAED 1.8M1,677Off-plan
2026-08-272 B/R1,095 sqftAED 1.8M1,670Off-plan
2026-08-062 B/R1,155 sqftAED 1.6M1,428Off-plan
2026-07-172 B/R1,095 sqftAED 1.7M1,531Off-plan
2026-07-111 B/R820 sqftAED 1.3M1,549Off-plan
2026-06-272 B/R1,240 sqftAED 1.7M1,403Off-plan
2026-06-222 B/R1,326 sqftAED 1.9M1,404Off-plan
2026-06-192 B/R1,039 sqftAED 1.7M1,596Off-plan
2026-06-141 B/R820 sqftAED 1.4M1,697Off-plan
2026-06-141 B/R745 sqftAED 1.3M1,729Off-plan
2026-06-141 B/R681 sqftAED 1.1M1,578Off-plan
2026-06-141 B/R820 sqftAED 1.4M1,650Off-plan
2026-06-142 B/R1,481 sqftAED 2.0M1,364Off-plan
2026-06-131 B/R820 sqftAED 1.3M1,642Off-plan
2026-06-13NA2,980 sqftAED 7.3M2,442Off-plan
2026-06-131 B/R820 sqftAED 1.4M1,689Off-plan
2026-06-131 B/R820 sqftAED 1.2M1,508Off-plan
2026-06-131 B/R820 sqftAED 1.4M1,699Off-plan
2026-06-132 B/R1,039 sqftAED 1.7M1,592Off-plan
2026-05-142 B/R1,039 sqftAED 1.7M1,600Off-plan
2026-04-30NA5,344 sqftAED 11.6M2,174Off-plan
2026-04-29NA5,966 sqftAED 13.3M2,229Off-plan
2026-04-251 B/R820 sqftAED 1.5M1,792Off-plan
2026-04-082 B/R1,039 sqftAED 1.6M1,572Off-plan
2026-04-082 B/R1,038 sqftAED 1.5M1,418Off-plan
2026-03-312 B/R1,481 sqftAED 2.1M1,406Off-plan
2026-03-231 B/R860 sqftAED 1.3M1,528Off-plan
2026-03-231 B/R820 sqftAED 1.3M1,618Off-plan
2026-03-232 B/R1,095 sqftAED 1.8M1,604Off-plan
2026-03-232 B/R1,095 sqftAED 1.8M1,605Off-plan
2026-02-262 B/R1,326 sqftAED 1.9M1,416Off-plan
2026-02-18NA4,988 sqftAED 10.1M2,025Off-plan
2026-02-16Studio401 sqftAED 712,3281,776Off-plan
2026-02-161 B/R820 sqftAED 1.3M1,588Off-plan
2026-02-162 B/R1,481 sqftAED 2.1M1,412Off-plan
2026-02-161 B/R789 sqftAED 1.3M1,645Off-plan
2026-01-29Studio347 sqftAED 699,5342,016Off-plan
2026-01-292 B/R1,095 sqftAED 1.7M1,563Off-plan
2026-01-291 B/R1,341 sqftAED 1.4M1,015Off-plan
2026-01-292 B/R1,326 sqftAED 1.9M1,430Off-plan

Source: DLD registered sale transactions. Floor and unit numbers aren’t published in the public transaction feed, so they’re not shown.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
HRE REAL ESTATE DEVELOPMENT L.L.C
Area
Al Barsha South Fourth
Master project
Project type
Normal
Start date
2024-06-01
Planned handover
2026-06-01
Last inspection
2026-08-27
Project value
AED 215.2M
Units
563
Villas
0
Buildings
0
DLD project number
3058

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
3058
Registered with DLD
2024-05-15
Regulator
Trakhees
Escrow account no.
0012157179015

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Al Barsha South Fourth · See every project on the construction map →

Skyhills III by HRE: frequently asked questions — answers update daily from registry data

When will Skyhills III by HRE be handed over?
The developer's planned handover for Skyhills III by HRE is 2026-06-01. Planned dates can move — track the project to be alerted the moment the official date changes.
Is Skyhills III by HRE delayed?
Skyhills III by HRE is 111 days past its planned handover of 2026-06-01 and still under construction. Most Dubai off-plan contracts include a grace period (often 6–12 months) beyond the anticipated date — see The Late List for how it compares.
Who is the developer of Skyhills III by HRE, and do they deliver on time?
Skyhills III by HRE is developed by HRE REAL ESTATE DEVELOPMENT L.L.C. On our Developer Reliability Index they score 80/100 (B Minor slippage), based on how much of their active portfolio is past its planned handover in the official registry.
What are real sale prices in Skyhills III by HRE?
Registered DLD sales in Skyhills III by HRE show a median of AED 1,598/sqft across 48 transactions since 2026-01-07. These are actual registered sales, not asking prices — the full breakdown is on this page.
Where is Skyhills III by HRE located?
Skyhills III by HRE is located in Al Barsha South Fourth, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Skyhills III by HRE?
Skyhills III by HRE comprises 563 units (normal), per the DLD registry.
Can I see real construction photos of Skyhills III by HRE?
Yes — this page carries 61 official construction photos taken during Dubai Land Department inspections, newest from 2026-09-01, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in Skyhills III by HRE?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for Skyhills III by HRE go?
Only into the project's DLD-registered escrow account (no. 0012157179015). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on Skyhills III by HRE?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Skyhills III by HRE's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE215.5%2026-06-01
2026-08-05ACTIVE215.5%2026-06-01
2026-08-06ACTIVE215.5%2026-06-01
2026-08-08ACTIVE215.5%2026-06-01
2026-08-09ACTIVE215.5%2026-06-01
2026-08-10ACTIVE215.5%2026-06-01
2026-08-11ACTIVE215.5%2026-06-01
2026-08-12ACTIVE215.5%2026-06-01
2026-08-13ACTIVE215.5%2026-06-01
2026-08-14ACTIVE215.5%2026-06-01
2026-08-15ACTIVE215.5%2026-06-01
2026-08-16ACTIVE215.5%2026-06-01
2026-08-17ACTIVE215.5%2026-06-01
2026-08-18ACTIVE215.5%2026-06-01
2026-08-19ACTIVE215.5%2026-06-01
2026-08-20ACTIVE215.5%2026-06-01
2026-08-21ACTIVE215.5%2026-06-01
2026-08-22ACTIVE215.5%2026-06-01
2026-08-23ACTIVE215.5%2026-06-01
2026-08-24ACTIVE215.5%2026-06-01
2026-08-25ACTIVE215.5%2026-06-01
2026-08-26ACTIVE215.5%2026-06-01
2026-08-27ACTIVE215.5%2026-06-01
2026-08-28ACTIVE215.5%2026-06-01
2026-08-29ACTIVE215.5%2026-06-01
2026-08-30ACTIVE215.5%2026-06-01
2026-08-31ACTIVE215.5%2026-06-01
2026-09-01ACTIVE215.5%2026-06-01
2026-09-02ACTIVE215.5%2026-06-01
2026-09-03ACTIVE215.5%2026-06-01
2026-09-04ACTIVE235.9%2026-06-01
2026-09-05ACTIVE235.9%2026-06-01
2026-09-06ACTIVE235.9%2026-06-01
2026-09-07ACTIVE235.9%2026-06-01
2026-09-08ACTIVE235.9%2026-06-01
2026-09-09ACTIVE235.9%2026-06-01
2026-09-10ACTIVE235.9%2026-06-01
2026-09-11ACTIVE235.9%2026-06-01
2026-09-12ACTIVE235.9%2026-06-01
2026-09-13ACTIVE235.9%2026-06-01
2026-09-14ACTIVE235.9%2026-06-01
2026-09-15ACTIVE235.9%2026-06-01
2026-09-16ACTIVE235.9%2026-06-01
2026-09-17ACTIVE235.9%2026-06-01
2026-09-18ACTIVE235.9%2026-06-01
2026-09-19ACTIVE235.9%2026-06-01
2026-09-20ACTIVE235.9%2026-06-01
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.
Track Skyhills III by HRE