Planned handover2026-03-31
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2024-05-31
in the DLD registry
Today
65.7%
last inspected 2026-06-10
Pace forecast
Day 2 of 7
unlocks as daily tracking accrues
Planned handover
2026-03-31
developer's official date

Watch it rise — one frame per DLD inspection

Palatium Residences on 2024-05-15
2024-05-15 · 0.0% complete
1 / 4

Real sale prices 36 registered DLD sales since 2026-01-08

AED 1,248/sqft
Median sale price
36
Registered sales
36
Sales, last 12 months
Unit typeSalesMedian AED/sqftMedian price
1 B/R281,248AED 1.1M
3 B/R41,252AED 1.6M
Studio21,601AED 668,270
2 B/R2771AED 1.2M

Source: DLD registered sale transactions for this project.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
AHMADYAR REAL ESTATE DEVELOPMENT L.L.C
Area
Al Barsha South Fourth
Master project
Project type
Normal
Start date
2024-05-31
Planned handover
2026-03-31
Last inspection
2026-06-10
Project value
AED 68.5M
Units
151
Villas
0
Buildings
0
DLD project number
3065

Palatium Residences: frequently asked questions — answers update daily from registry data

When will Palatium Residences be handed over?
The developer's planned handover for Palatium Residences is 2026-03-31; construction is currently 66% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on Palatium Residences?
Palatium Residences is 65.7% complete according to the Dubai Land Department's inspection of 2026-06-10.
Is Palatium Residences delayed?
Palatium Residences is 128 days past its planned handover of 2026-03-31 and still under construction. Most Dubai off-plan contracts include a grace period (often 6–12 months) beyond the anticipated date — see The Late List for how it compares.
Who is the developer of Palatium Residences, and do they deliver on time?
Palatium Residences is developed by AHMADYAR REAL ESTATE DEVELOPMENT L.L.C. On our Developer Reliability Index they score 73/100 (B Minor slippage), based on how much of their active portfolio is past its planned handover in the official registry.
What are real sale prices in Palatium Residences?
Registered DLD sales in Palatium Residences show a median of AED 1,248/sqft across 36 transactions since 2026-01-08. These are actual registered sales, not asking prices — the full breakdown is on this page.
Where is Palatium Residences located?
Palatium Residences is located in Al Barsha South Fourth, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Palatium Residences?
Palatium Residences comprises 151 units (normal), per the DLD registry.
Can I see real construction photos of Palatium Residences?
Yes — this page carries 40 official construction photos taken during Dubai Land Department inspections, newest from 2026-06-19, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in Palatium Residences?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
How do I get alerts when something changes on Palatium Residences?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Palatium Residences's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE65.7%2026-03-31
2026-08-05ACTIVE65.7%2026-03-31
2026-08-06ACTIVE65.7%2026-03-31
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.