Home / Projects / Binghatti Ghost
Latest DLD inspection photo of Binghatti Ghost
Latest inspection · 2026-09-21 · DLD inspection
Planned handover2026-09-23
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2024-07-31
in the DLD registry
Today
100.0%
last inspected 2026-09-17
Pace forecast
Day 7 of 7
unlocks as daily tracking accrues
Planned handover
2026-09-23
developer's official date

Investor snapshot — estimated yield

4.5%estimated gross rental yield

1,871/sqft median sale price (this project)

85/sqft/yr median rent in Al Jadaf

Estimate: area-wide median rent ÷ this project’s median sale price, from Dubai Land Department records. Actual rent varies by unit, floor and finish.

How Binghatti Ghost compares

Similar off-plan projects in Al Jadaf — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about Binghatti Ghost

Considering buying in Binghatti Ghost? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Watch it rise — one frame per DLD inspection

Binghatti Ghost on 2024-07-23
2024-07-23 · 0.0% complete
1 / 5

Building & unit mix — from DLD project records

27
Floors
785
Total units
1
Building
UsageUnit typeUnits
CommercialUnspecified6
ResidentialStudio440
Residential1 B/R239
Residential2 B/R40
Residential3 B/R60

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Real sale prices — 59 registered DLD sales since 2026-01-07

AED 1,871/sqft
Median sale price
59
Registered sales
59
Sales, last 12 months
Unit typeSalesMedian AED/sqftMedian price
Studio221,876AED 825,000
1 B/R141,533AED 1.2M
2 B/R112,042AED 2.6M
3 B/R112,192AED 4.1M
NA13,378AED 2.4M

Source: DLD registered sale transactions for this project.

Prices by unit size — vs the Al Jadaf average

BedsUnits soldSize rangeMedian priceAED/sqftArea avgPremium vs area
Studio22348–473 sqftAED 825,0001,8761,902-1%
1 B/R14732–912 sqftAED 1.2M1,5331,620-5%
2 B/R111,285–1,355 sqftAED 2.6M2,0421,598+28%
3 B/R111,597–2,367 sqftAED 4.1M2,1922,1990%
NA1719–719 sqftAED 2.4M3,378——

Median AED/sqft of DLD-registered sales in this project vs all sales in Al Jadaf for the same unit type. “Premium vs area” is how much more (or less) buyers pay here than the neighbourhood average.

Sale price history — 686 sales, median AED/sqft by year

+21% median price growth from 2024 to 2026 · 100% of sales were off-plan

YearMedian AED/sqftSalesYear-on-yearSince launch
2024launch1,623250——
20252,239415+38%+38%
20261,97021-12%+21%

Median AED/sqft of DLD-registered sales each year (years with 3+ sales); the earliest year on record approximates launch pricing. “Year-on-year” compares each year to the one before it, “since launch” to the first year. Source: Dubai Land Department transaction records.

Available layouts — check current availability & price

Layouts registered in Binghatti Ghost, grouped by size. We’ll confirm current availability, floor and price with a RERA-licensed agent — we don’t hold live developer inventory, so these are representative configurations, not a live unit list.

BedsSizeTypical priceAED/sqftRegistered
Studio348 sqftAED 784K2,2453
Studio436 sqftAED 814K1,8715
Studio448 sqftAED 830K1,85213
Studio473 sqftAED 1.2M2,5891
1 B/R737 sqftAED 1.2M1,6283
1 B/R776 sqftAED 1.2M1,5723
1 B/R856 sqftAED 1.3M1,4604
1 B/R873 sqftAED 1.2M1,3743
1 B/R912 sqftAED 1.2M1,3161
2 B/R1,285 sqftAED 2.6M2,0425
2 B/R1,290 sqftAED 2.1M1,6294
2 B/R1,316 sqftAED 3.1M2,3281
2 B/R1,355 sqftAED 3.0M2,2421
3 B/R1,603 sqftAED 3.0M1,8723

Recent registered sales — individual DLD transactions, newest first

DateBedsSizePriceAED/sqftType
2026-11-06Studio434 sqftAED 780,0001,798Resale
2026-11-051 B/R776 sqftAED 1.2M1,572Resale
2026-11-041 B/R856 sqftAED 1.3M1,460Resale
2026-11-031 B/R873 sqftAED 1.2M1,374Resale
2026-11-03Studio446 sqftAED 750,0001,681Resale
2026-11-031 B/R873 sqftAED 1.2M1,374Resale
2026-10-301 B/R784 sqftAED 1.5M1,978Resale
2026-10-302 B/R1,286 sqftAED 2.9M2,284Resale
2026-10-30Studio448 sqftAED 800,0001,785Resale
2026-10-30Studio437 sqftAED 820,0001,878Resale
2026-10-28Studio446 sqftAED 790,0001,770Resale
2026-10-26Studio462 sqftAED 1.2M2,649Resale
2026-10-233 B/R1,904 sqftAED 4.2M2,192Resale
2026-10-211 B/R776 sqftAED 1.2M1,495Resale
2026-10-193 B/R1,637 sqftAED 4.1M2,505Resale
2026-10-162 B/R1,285 sqftAED 2.0M1,556Resale
2026-10-133 B/R1,904 sqftAED 4.2M2,199Resale
2026-10-12Studio452 sqftAED 860,0001,901Resale
2026-10-091 B/R856 sqftAED 1.2M1,401Resale
2026-10-07Studio446 sqftAED 835,0001,874Resale
2026-09-183 B/R1,904 sqftAED 4.3M2,245Off-plan
2026-09-173 B/R1,637 sqftAED 2.9M1,741Off-plan
2026-09-171 B/R850 sqftAED 1.3M1,589Off-plan
2026-09-173 B/R2,367 sqftAED 4.3M1,817Off-plan
2026-09-172 B/R1,285 sqftAED 2.7M2,091Off-plan
2026-09-173 B/R1,597 sqftAED 2.9M1,785Off-plan
2026-09-172 B/R1,285 sqftAED 2.6M2,042Off-plan
2026-09-15Studio448 sqftAED 800,0001,785Off-plan
2026-09-15Studio448 sqftAED 825,0001,841Off-plan
2026-09-091 B/R732 sqftAED 1.2M1,612Off-plan
2026-09-071 B/R856 sqftAED 1.3M1,460Off-plan
2026-08-271 B/R737 sqftAED 1.2M1,628Off-plan
2026-08-212 B/R1,290 sqftAED 2.0M1,551Off-plan
2026-08-19Studio348 sqftAED 713,8002,051Off-plan
2026-08-183 B/R1,603 sqftAED 3.0M1,872Off-plan
2026-08-183 B/R1,897 sqftAED 4.5M2,365Off-plan
2026-08-13Studio348 sqftAED 860,0002,471Off-plan
2026-08-10Studio447 sqftAED 825,0001,847Off-plan
2026-08-05Studio447 sqftAED 880,0001,970Off-plan
2026-08-033 B/R1,604 sqftAED 4.1M2,556Off-plan

Source: DLD registered sale transactions. Floor and unit numbers aren’t published in the public transaction feed, so they’re not shown.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
Binghatti Developers FZE
Area
Al Jadaf
Master project
—
Project type
Normal
Start date
2024-07-31
Planned handover
2026-09-23
Last inspection
2026-09-17
Project value
AED 300.0M
Units
1654
Villas
0
Buildings
0
DLD project number
3192

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
3192
Registered with DLD
2024-09-10
Regulator
Dubai Development Authority (DDA)
Escrow account no.
29125362

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Al Jadaf · See every project on the construction map →

Binghatti Ghost: frequently asked questions — answers update daily from registry data

When will Binghatti Ghost be handed over?
The developer's planned handover for Binghatti Ghost is 2026-09-23; construction is currently 100% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on Binghatti Ghost?
Binghatti Ghost is 100.0% complete according to the Dubai Land Department's inspection of 2026-09-17.
Who is the developer of Binghatti Ghost, and do they deliver on time?
Binghatti Ghost is developed by Binghatti Developers FZE. On our Developer Reliability Index they score 66/100 (C — Slipping), based on how much of their active portfolio is past its planned handover in the official registry.
What are real sale prices in Binghatti Ghost?
Registered DLD sales in Binghatti Ghost show a median of AED 1,871/sqft across 59 transactions since 2026-01-07. These are actual registered sales, not asking prices — the full breakdown is on this page.
Where is Binghatti Ghost located?
Binghatti Ghost is located in Al Jadaf, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Binghatti Ghost?
Binghatti Ghost comprises 1654 units (normal), per the DLD registry.
Can I see real construction photos of Binghatti Ghost?
Yes — this page carries 40 official construction photos taken during Dubai Land Department inspections, newest from 2026-09-21, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in Binghatti Ghost?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for Binghatti Ghost go?
Only into the project's DLD-registered escrow account (no. 29125362). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on Binghatti Ghost?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Binghatti Ghost's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE67.9%2026-03-31
2026-08-05ACTIVE67.9%2026-03-31
2026-08-06ACTIVE67.9%2026-03-31
2026-08-08ACTIVE67.9%2026-03-31
2026-08-09ACTIVE67.9%2026-03-31
2026-08-10ACTIVE67.9%2026-03-31
2026-08-11ACTIVE67.9%2026-03-31
2026-08-12ACTIVE98.9%2026-03-31
2026-08-13ACTIVE98.9%2026-03-31
2026-08-14ACTIVE98.9%2026-03-31
2026-08-15ACTIVE98.9%2026-03-31
2026-08-16ACTIVE98.9%2026-03-31
2026-08-17ACTIVE98.9%2026-03-31
2026-08-18ACTIVE98.9%2026-03-31
2026-08-19ACTIVE98.9%2026-03-31
2026-08-20ACTIVE98.9%2026-03-31
2026-08-21ACTIVE98.9%2026-03-31
2026-08-22ACTIVE98.9%2026-03-31
2026-08-23ACTIVE98.9%2026-03-31
2026-08-24ACTIVE98.9%2026-03-31
2026-08-25ACTIVE98.9%2026-03-31
2026-08-26ACTIVE98.9%2026-03-31
2026-08-27ACTIVE98.9%2026-03-31
2026-08-28ACTIVE98.9%2026-03-31
2026-08-29ACTIVE98.9%2026-03-31
2026-08-30ACTIVE98.9%2026-03-31
2026-08-31ACTIVE98.9%2026-03-31
2026-09-01ACTIVE98.9%2026-03-31
2026-09-02ACTIVE98.9%2026-03-31
2026-09-03ACTIVE98.9%2026-03-31
2026-09-04ACTIVE98.9%2026-03-31
2026-09-05ACTIVE98.9%2026-03-31
2026-09-06ACTIVE98.9%2026-03-31
2026-09-07ACTIVE98.9%2026-03-31
2026-09-08ACTIVE98.9%2026-03-31
2026-09-09ACTIVE98.9%2026-03-31
2026-09-10ACTIVE98.9%2026-03-31
2026-09-11ACTIVE98.9%2026-03-31
2026-09-12ACTIVE98.9%2026-03-31
2026-09-13ACTIVE98.9%2026-03-31
2026-09-14ACTIVE98.9%2026-03-31
2026-09-15ACTIVE98.9%2026-03-31
2026-09-16ACTIVE98.9%2026-03-31
2026-09-17ACTIVE98.9%2026-03-31
2026-09-18ACTIVE98.9%2026-03-31
2026-09-19ACTIVE98.9%2026-03-31
2026-09-20ACTIVE98.9%2026-03-31
2026-09-21ACTIVE98.9%2026-03-31
2026-09-22ACTIVE98.9%2026-03-31
2026-09-23ACTIVE98.9%2026-03-31
2026-09-24FINISHED100.0%2026-09-23
2026-09-25FINISHED100.0%2026-09-23
2026-09-26FINISHED100.0%2026-09-23
2026-09-27FINISHED100.0%2026-09-23
2026-09-28FINISHED100.0%2026-09-23
2026-09-29FINISHED100.0%2026-09-23
2026-09-30FINISHED100.0%2026-09-23
2026-10-01FINISHED100.0%2026-09-23
2026-10-02FINISHED100.0%2026-09-23
2026-10-03FINISHED100.0%2026-09-23
2026-10-04FINISHED100.0%2026-09-23
2026-10-05FINISHED100.0%2026-09-23
2026-10-06FINISHED100.0%2026-09-23
2026-10-07FINISHED100.0%2026-09-23
2026-10-08FINISHED100.0%2026-09-23
2026-10-09FINISHED100.0%2026-09-23
2026-10-10FINISHED100.0%2026-09-23
2026-10-11FINISHED100.0%2026-09-23
2026-10-12FINISHED100.0%2026-09-23
2026-10-13FINISHED100.0%2026-09-23
2026-10-14FINISHED100.0%2026-09-23
2026-10-15FINISHED100.0%2026-09-23
2026-10-16FINISHED100.0%2026-09-23
2026-10-17FINISHED100.0%2026-09-23
2026-10-18FINISHED100.0%2026-09-23
2026-10-19FINISHED100.0%2026-09-23
2026-10-20FINISHED100.0%2026-09-23
2026-10-21FINISHED100.0%2026-09-23
2026-10-22FINISHED100.0%2026-09-23
2026-10-23FINISHED100.0%2026-09-23
2026-10-24FINISHED100.0%2026-09-23
2026-10-25FINISHED100.0%2026-09-23
2026-10-26FINISHED100.0%2026-09-23
2026-10-27FINISHED100.0%2026-09-23
2026-10-28FINISHED100.0%2026-09-23
2026-10-29FINISHED100.0%2026-09-23
2026-10-30FINISHED100.0%2026-09-23
2026-10-31FINISHED100.0%2026-09-23
2026-11-01FINISHED100.0%2026-09-23
2026-11-02FINISHED100.0%2026-09-23
2026-11-03FINISHED100.0%2026-09-23
2026-11-04FINISHED100.0%2026-09-23
2026-11-05FINISHED100.0%2026-09-23
2026-11-06FINISHED100.0%2026-09-23
2026-11-07FINISHED100.0%2026-09-23

Change events

DetectedEventChange
2026-09-24HANDOVER_SLIP2026-03-31 → 2026-09-23
2026-09-24STATUS_CHANGEACTIVE → FINISHED
2026-09-24PROGRESS98.93 → 100.00
2026-08-12PROGRESS67.87 → 98.93
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.
Track Binghatti Ghost