Home / Projects / ENSO AMBER
Latest DLD inspection photo of ENSO AMBER
Latest inspection · 2026-07-14 · DLD inspection
Planned handover2026-06-30
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2024-09-01
in the DLD registry
Today
11.3%
last inspected 2026-07-07
Pace forecast
Day 2 of 7
unlocks as daily tracking accrues
Planned handover
2026-06-30
developer's official date

Watch it rise — one frame per DLD inspection

ENSO AMBER on 2024-09-10
2024-09-10 · 0.0% complete
1 / 4

Real sale prices 29 registered DLD sales since 2026-01-20

AED 2,159/sqft
Median sale price
29
Registered sales
29
Sales, last 12 months
Unit typeSalesMedian AED/sqftMedian price
1 B/R202,127AED 1.6M
Studio82,161AED 1.1M
3 B/R12,003AED 3.5M

Source: DLD registered sale transactions for this project.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
ENSO DEVELOPMENT L.L.C
Area
Al Satwa
Master project
Project type
Normal
Start date
2024-09-01
Planned handover
2026-06-30
Last inspection
2026-07-07
Project value
AED 40.0M
Units
71
Villas
0
Buildings
0
DLD project number
3250

ENSO AMBER: frequently asked questions — answers update daily from registry data

When will ENSO AMBER be handed over?
The developer's planned handover for ENSO AMBER is 2026-06-30; construction is currently 11% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on ENSO AMBER?
ENSO AMBER is 11.3% complete according to the Dubai Land Department's inspection of 2026-07-07.
Is ENSO AMBER delayed?
ENSO AMBER is 37 days past its planned handover of 2026-06-30 and still under construction. Most Dubai off-plan contracts include a grace period (often 6–12 months) beyond the anticipated date — see The Late List for how it compares.
Who is the developer of ENSO AMBER, and do they deliver on time?
ENSO AMBER is developed by ENSO DEVELOPMENT L.L.C. On our Developer Reliability Index they score 70/100 (B Minor slippage), based on how much of their active portfolio is past its planned handover in the official registry.
What are real sale prices in ENSO AMBER?
Registered DLD sales in ENSO AMBER show a median of AED 2,159/sqft across 29 transactions since 2026-01-20. These are actual registered sales, not asking prices — the full breakdown is on this page.
Where is ENSO AMBER located?
ENSO AMBER is located in Al Satwa, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in ENSO AMBER?
ENSO AMBER comprises 71 units (normal), per the DLD registry.
Can I see real construction photos of ENSO AMBER?
Yes — this page carries 26 official construction photos taken during Dubai Land Department inspections, newest from 2026-07-14, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in ENSO AMBER?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
How do I get alerts when something changes on ENSO AMBER?
Use the free Track this project form on this page. We check the official registry every day and email you the moment ENSO AMBER's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE11.3%2026-06-30
2026-08-05ACTIVE11.3%2026-06-30
2026-08-06ACTIVE11.3%2026-06-30
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.
Track ENSO AMBER