Home / Projects / Binghatti Etherea
ACTIVE▲ +7.2% this week

Binghatti Etherea

بن غاطي إيثيريا
Latest DLD inspection photo of Binghatti Etherea
Latest inspection · 2026-09-15 · DLD inspection
Planned handover2027-12-31
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2026-01-01
in the DLD registry
Today
7.2%
last inspected 2026-09-09
At the current pace
Planned handover
2027-12-31
developer's official date

Investor snapshot — estimated yield

3.9%estimated gross rental yield

2,275/sqft median sale price (this project)

89/sqft/yr median rent in Al Barsha South Fourth

Estimate: area-wide median rent ÷ this project’s median sale price, from Dubai Land Department records. Actual rent varies by unit, floor and finish.

How Binghatti Etherea compares

Similar off-plan projects in Al Barsha South Fourth — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about Binghatti Etherea

Considering buying in Binghatti Etherea? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Building & unit mix — from DLD project records

31
Floors
287
Total units
1
Building
UsageUnit typeUnits
CommercialUnspecified5
ResidentialStudio64
Residential1 B/R134
Residential2 B/R84

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Real sale prices 58 registered DLD sales since 2026-03-17

AED 2,275/sqft
Median sale price
58
Registered sales
58
Sales, last 12 months
Unit typeSalesMedian AED/sqftMedian price
Studio392,281AED 766,999
1 B/R161,929AED 1.2M
NA22,600AED 4.1M
2 B/R11,828AED 1.6M

Source: DLD registered sale transactions for this project.

Prices by unit size — vs the Al Barsha South Fourth average

BedsUnits soldSize rangeMedian priceAED/sqftArea avgPremium vs area
Studio39336422 sqftAED 766,9992,281
1 B/R16575655 sqftAED 1.2M1,929
2 B/R1875875 sqftAED 1.6M1,828
NA21,3501,827 sqftAED 4.1M2,600

Median AED/sqft of DLD-registered sales in this project vs all sales in Al Barsha South Fourth for the same unit type. “Premium vs area” is how much more (or less) buyers pay here than the neighbourhood average.

Available layouts — check current availability & price

Layouts registered in Binghatti Etherea, grouped by size. We’ll confirm current availability, floor and price with a RERA-licensed agent — we don’t hold live developer inventory, so these are representative configurations, not a live unit list.

BedsSizeTypical priceAED/sqftRegistered
Studio336 sqftAED 767K2,28237
Studio420 sqftAED 770K1,8312
1 B/R577 sqftAED 1.2M2,1144
1 B/R655 sqftAED 1.2M1,79412
2 B/R875 sqftAED 1.6M1,8281
NA1,350 sqftAED 3.6M2,7001
NA1,827 sqftAED 4.6M2,5001

Recent registered sales — individual DLD transactions, newest first

DateBedsSizePriceAED/sqftType
2026-09-171 B/R655 sqftAED 1.0M1,527Off-plan
2026-09-171 B/R655 sqftAED 1.0M1,527Off-plan
2026-09-17Studio336 sqftAED 700,0002,085Off-plan
2026-09-171 B/R655 sqftAED 1.1M1,679Off-plan
2026-09-171 B/R655 sqftAED 1.1M1,603Off-plan
2026-09-111 B/R655 sqftAED 1.3M2,017Off-plan
2026-09-11Studio419 sqftAED 750,0001,790Off-plan
2026-09-11Studio336 sqftAED 764,9992,275Off-plan
2026-09-11Studio336 sqftAED 769,9992,290Off-plan
2026-09-10Studio336 sqftAED 765,9992,278Off-plan
2026-09-10Studio422 sqftAED 789,9991,872Off-plan
2026-09-091 B/R655 sqftAED 1.3M1,908Off-plan
2026-09-07Studio336 sqftAED 765,9992,278Off-plan
2026-09-072 B/R875 sqftAED 1.6M1,828Off-plan
2026-09-07Studio336 sqftAED 768,9992,288Off-plan
2026-09-041 B/R655 sqftAED 1.3M2,016Off-plan
2026-09-04Studio336 sqftAED 769,9992,290Off-plan
2026-09-03Studio336 sqftAED 769,9992,294Off-plan
2026-09-03Studio336 sqftAED 766,9992,281Off-plan
2026-09-02Studio336 sqftAED 740,1602,201Off-plan
2026-09-02Studio336 sqftAED 767,9992,284Off-plan
2026-09-02Studio336 sqftAED 680,0002,022Off-plan
2026-08-19Studio336 sqftAED 770,9992,293Off-plan
2026-08-17Studio336 sqftAED 766,9992,282Off-plan
2026-08-17Studio337 sqftAED 700,0002,076Off-plan
2026-08-17Studio337 sqftAED 769,9992,283Off-plan
2026-08-171 B/R655 sqftAED 1.3M1,950Off-plan
2026-08-17Studio336 sqftAED 765,9992,278Off-plan
2026-08-12Studio336 sqftAED 728,6492,167Off-plan
2026-08-03Studio336 sqftAED 769,9992,291Off-plan
2026-07-291 B/R655 sqftAED 1.0M1,527Off-plan
2026-07-25NA1,827 sqftAED 4.6M2,500Off-plan
2026-07-20NA1,350 sqftAED 3.6M2,700Off-plan
2026-07-201 B/R575 sqftAED 1.1M1,826Off-plan
2026-06-29Studio337 sqftAED 766,9992,274Off-plan
2026-06-29Studio336 sqftAED 769,9992,290Off-plan
2026-06-24Studio336 sqftAED 767,9992,285Off-plan
2026-06-24Studio336 sqftAED 700,0002,085Off-plan
2026-06-24Studio337 sqftAED 766,9992,274Off-plan
2026-06-24Studio337 sqftAED 770,9992,286Off-plan

Source: DLD registered sale transactions. Floor and unit numbers aren’t published in the public transaction feed, so they’re not shown.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
Binghatti Developers FZE
Area
Al Barsha South Fourth
Master project
Project type
Normal
Start date
2026-01-01
Planned handover
2027-12-31
Last inspection
2026-09-09
Project value
AED 115.0M
Units
287
Villas
0
Buildings
0
DLD project number
4303

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
4303
Registered with DLD
2026-01-27
Regulator
Trakhees
Escrow account no.
019500000878

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Al Barsha South Fourth · See every project on the construction map →

Binghatti Etherea: frequently asked questions — answers update daily from registry data

When will Binghatti Etherea be handed over?
The developer's planned handover for Binghatti Etherea is 2027-12-31; construction is currently 7% complete. At the observed construction pace, our independent forecast is 2028-05-11.
How far along is construction on Binghatti Etherea?
Binghatti Etherea is 7.2% complete according to the Dubai Land Department's inspection of 2026-09-09. Progress moved up 7.2 percentage points at the latest inspection.
Is Binghatti Etherea delayed?
As of today, Binghatti Etherea has not passed its planned handover date of 2027-12-31. We compare the official date against the calendar daily and record every change on this page.
Who is the developer of Binghatti Etherea, and do they deliver on time?
Binghatti Etherea is developed by Binghatti Developers FZE. On our Developer Reliability Index they score 66/100 (C Slipping), based on how much of their active portfolio is past its planned handover in the official registry.
What are real sale prices in Binghatti Etherea?
Registered DLD sales in Binghatti Etherea show a median of AED 2,275/sqft across 58 transactions since 2026-03-17. These are actual registered sales, not asking prices — the full breakdown is on this page.
Where is Binghatti Etherea located?
Binghatti Etherea is located in Al Barsha South Fourth, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Binghatti Etherea?
Binghatti Etherea comprises 287 units (normal), per the DLD registry.
Can I see real construction photos of Binghatti Etherea?
Yes — this page carries 7 official construction photos taken during Dubai Land Department inspections, newest from 2026-09-15, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in Binghatti Etherea?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for Binghatti Etherea go?
Only into the project's DLD-registered escrow account (no. 019500000878). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on Binghatti Etherea?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Binghatti Etherea's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE0.0%2027-12-31
2026-08-05ACTIVE0.0%2027-12-31
2026-08-06ACTIVE0.0%2027-12-31
2026-08-08ACTIVE0.0%2027-12-31
2026-08-09ACTIVE0.0%2027-12-31
2026-08-10ACTIVE0.0%2027-12-31
2026-08-11ACTIVE0.0%2027-12-31
2026-08-12ACTIVE0.0%2027-12-31
2026-08-13ACTIVE0.0%2027-12-31
2026-08-14ACTIVE0.0%2027-12-31
2026-08-15ACTIVE0.0%2027-12-31
2026-08-16ACTIVE0.0%2027-12-31
2026-08-17ACTIVE0.0%2027-12-31
2026-08-18ACTIVE0.0%2027-12-31
2026-08-19ACTIVE0.0%2027-12-31
2026-08-20ACTIVE0.0%2027-12-31
2026-08-21ACTIVE0.0%2027-12-31
2026-08-22ACTIVE0.0%2027-12-31
2026-08-23ACTIVE0.0%2027-12-31
2026-08-24ACTIVE0.0%2027-12-31
2026-08-25ACTIVE0.0%2027-12-31
2026-08-26ACTIVE0.0%2027-12-31
2026-08-27ACTIVE0.0%2027-12-31
2026-08-28ACTIVE0.0%2027-12-31
2026-08-29ACTIVE0.0%2027-12-31
2026-08-30ACTIVE0.0%2027-12-31
2026-08-31ACTIVE0.0%2027-12-31
2026-09-01ACTIVE0.0%2027-12-31
2026-09-02ACTIVE0.0%2027-12-31
2026-09-03ACTIVE0.0%2027-12-31
2026-09-04ACTIVE0.0%2027-12-31
2026-09-05ACTIVE0.0%2027-12-31
2026-09-06ACTIVE0.0%2027-12-31
2026-09-07ACTIVE0.0%2027-12-31
2026-09-08ACTIVE0.0%2027-12-31
2026-09-09ACTIVE0.0%2027-12-31
2026-09-10ACTIVE0.0%2027-12-31
2026-09-11ACTIVE0.0%2027-12-31
2026-09-12ACTIVE0.0%2027-12-31
2026-09-13ACTIVE0.0%2027-12-31
2026-09-14ACTIVE0.0%2027-12-31
2026-09-15ACTIVE0.0%2027-12-31
2026-09-16ACTIVE0.0%2027-12-31
2026-09-17ACTIVE7.2%2027-12-31
2026-09-18ACTIVE7.2%2027-12-31
2026-09-19ACTIVE7.2%2027-12-31
2026-09-20ACTIVE7.2%2027-12-31

Change events

DetectedEventChange
2026-09-17PROGRESS0.007.24