Home / Projects / Samana Waves 2
Latest DLD inspection photo of Samana Waves 2
Latest inspection · 2026-06-19 · DLD inspection
Planned handover2026-03-20
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2023-09-21
in the DLD registry
Today
47.3%
last inspected 2026-05-13
Pace forecast
Day 2 of 7
unlocks as daily tracking accrues
Planned handover
2026-03-20
developer's official date

Watch it rise — one frame per DLD inspection

Samana Waves 2 on 2023-02-07
2023-02-07 · 0.0% complete
1 / 6

Real sale prices 4 registered DLD sales since 2026-03-11

AED 1,384/sqft
Median sale price
4
Registered sales
4
Sales, last 12 months
Unit typeSalesMedian AED/sqftMedian price
Studio21,384AED 649,041
1 B/R21,378AED 1.1M

Source: DLD registered sale transactions for this project.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
SAMANA SI HOLDING LIMITED DUBAI BRANCH
Area
Al Barsha South Fourth
Master project
Project type
Normal
Start date
2023-09-21
Planned handover
2026-03-20
Last inspection
2026-05-13
Project value
AED 40.0M
Units
173
Villas
0
Buildings
0
DLD project number
2574

Samana Waves 2: frequently asked questions — answers update daily from registry data

When will Samana Waves 2 be handed over?
The developer's planned handover for Samana Waves 2 is 2026-03-20; construction is currently 47% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on Samana Waves 2?
Samana Waves 2 is 47.3% complete according to the Dubai Land Department's inspection of 2026-05-13.
Is Samana Waves 2 delayed?
Samana Waves 2 is 139 days past its planned handover of 2026-03-20 and still under construction. Most Dubai off-plan contracts include a grace period (often 6–12 months) beyond the anticipated date — see The Late List for how it compares.
Who is the developer of Samana Waves 2, and do they deliver on time?
Samana Waves 2 is developed by SAMANA SI HOLDING LIMITED DUBAI BRANCH. On our Developer Reliability Index they score 45/100 (D Heavily delayed), based on how much of their active portfolio is past its planned handover in the official registry.
What are real sale prices in Samana Waves 2?
Registered DLD sales in Samana Waves 2 show a median of AED 1,384/sqft across 4 transactions since 2026-03-11. These are actual registered sales, not asking prices — the full breakdown is on this page.
Where is Samana Waves 2 located?
Samana Waves 2 is located in Al Barsha South Fourth, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Samana Waves 2?
Samana Waves 2 comprises 173 units (normal), per the DLD registry.
Can I see real construction photos of Samana Waves 2?
Yes — this page carries 37 official construction photos taken during Dubai Land Department inspections, newest from 2026-06-19, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in Samana Waves 2?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
How do I get alerts when something changes on Samana Waves 2?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Samana Waves 2's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE47.3%2026-03-20
2026-08-05ACTIVE47.3%2026-03-20
2026-08-06ACTIVE47.3%2026-03-20