Home / Projects / Cavara 42
Latest DLD inspection photo of Cavara 42
Latest inspection · 2026-06-05 · DLD inspection
Planned handover2026-05-02
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2024-09-17
in the DLD registry
Today
75.8%
last inspected 2026-06-03
Pace forecast
Day 7 of 7
unlocks as daily tracking accrues
Planned handover
2026-05-02
178 days overdue — developer's official date

How Cavara 42 compares

Similar off-plan projects in Al Barshaa South Third — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about Cavara 42

Considering buying in Cavara 42? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Watch it rise — one frame per DLD inspection

Cavara 42 on 2025-02-28
2025-02-28 · 3.0% complete
1 / 5

Building & unit mix — from DLD project records

10
Floors
49
Total units
1
Building
UsageUnit typeUnits
CommercialUnspecified7
Residential1 B/R14
Residential2 B/R28

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
CAVARA REAL ESTATE DEVELOPMENT L.L.C
Area
Al Barshaa South Third
Master project
—
Project type
Normal
Start date
2024-09-17
Planned handover
2026-05-02
Last inspection
2026-06-03
Project value
AED 33.3M
Units
49
Villas
0
Buildings
0
DLD project number
3588

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
3588
Registered with DLD
2025-04-10
Regulator
Dubai Development Authority (DDA)
Escrow account no.
0205915669003

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Al Barshaa South Third · See every project on the construction map →

Cavara 42: frequently asked questions — answers update daily from registry data

When will Cavara 42 be handed over?
The developer's planned handover for Cavara 42 is 2026-05-02; construction is currently 76% complete. Planned dates can move — track the project to be alerted the moment the official date changes.
How far along is construction on Cavara 42?
Cavara 42 is 75.8% complete according to the Dubai Land Department's inspection of 2026-06-03.
Is Cavara 42 delayed?
Cavara 42 is 178 days past its planned handover of 2026-05-02 and still under construction. Most Dubai off-plan contracts include a grace period (often 6–12 months) beyond the anticipated date — see The Late List for how it compares.
Who is the developer of Cavara 42, and do they deliver on time?
Cavara 42 is developed by CAVARA REAL ESTATE DEVELOPMENT L.L.C. On our Developer Reliability Index they score 58/100 (C — Slipping), based on how much of their active portfolio is past its planned handover in the official registry.
Where is Cavara 42 located?
Cavara 42 is located in Al Barshaa South Third, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Cavara 42?
Cavara 42 comprises 49 units (normal), per the DLD registry.
Can I see real construction photos of Cavara 42?
Yes — this page carries 36 official construction photos taken during Dubai Land Department inspections, newest from 2026-06-05, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in Cavara 42?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for Cavara 42 go?
Only into the project's DLD-registered escrow account (no. 0205915669003). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on Cavara 42?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Cavara 42's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE75.8%2026-05-02
2026-08-05ACTIVE75.8%2026-05-02
2026-08-06ACTIVE75.8%2026-05-02
2026-08-08ACTIVE75.8%2026-05-02
2026-08-09ACTIVE75.8%2026-05-02
2026-08-10ACTIVE75.8%2026-05-02
2026-08-11ACTIVE75.8%2026-05-02
2026-08-12ACTIVE75.8%2026-05-02
2026-08-13ACTIVE75.8%2026-05-02
2026-08-14ACTIVE75.8%2026-05-02
2026-08-15ACTIVE75.8%2026-05-02
2026-08-16ACTIVE75.8%2026-05-02
2026-08-17ACTIVE75.8%2026-05-02
2026-08-18ACTIVE75.8%2026-05-02
2026-08-19ACTIVE75.8%2026-05-02
2026-08-20ACTIVE75.8%2026-05-02
2026-08-21ACTIVE75.8%2026-05-02
2026-08-22ACTIVE75.8%2026-05-02
2026-08-23ACTIVE75.8%2026-05-02
2026-08-24ACTIVE75.8%2026-05-02
2026-08-25ACTIVE75.8%2026-05-02
2026-08-26ACTIVE75.8%2026-05-02
2026-08-27ACTIVE75.8%2026-05-02
2026-08-28ACTIVE75.8%2026-05-02
2026-08-29ACTIVE75.8%2026-05-02
2026-08-30ACTIVE75.8%2026-05-02
2026-08-31ACTIVE75.8%2026-05-02
2026-09-01ACTIVE75.8%2026-05-02
2026-09-02ACTIVE75.8%2026-05-02
2026-09-03ACTIVE75.8%2026-05-02
2026-09-04ACTIVE75.8%2026-05-02
2026-09-05ACTIVE75.8%2026-05-02
2026-09-06ACTIVE75.8%2026-05-02
2026-09-07ACTIVE75.8%2026-05-02
2026-09-08ACTIVE75.8%2026-05-02
2026-09-09ACTIVE75.8%2026-05-02
2026-09-10ACTIVE75.8%2026-05-02
2026-09-11ACTIVE75.8%2026-05-02
2026-09-12ACTIVE75.8%2026-05-02
2026-09-13ACTIVE75.8%2026-05-02
2026-09-14ACTIVE75.8%2026-05-02
2026-09-15ACTIVE75.8%2026-05-02
2026-09-16ACTIVE75.8%2026-05-02
2026-09-17ACTIVE75.8%2026-05-02
2026-09-18ACTIVE75.8%2026-05-02
2026-09-19ACTIVE75.8%2026-05-02
2026-09-20ACTIVE75.8%2026-05-02
2026-09-21ACTIVE75.8%2026-05-02
2026-09-22ACTIVE75.8%2026-05-02
2026-09-23ACTIVE75.8%2026-05-02
2026-09-24ACTIVE75.8%2026-05-02
2026-09-25ACTIVE75.8%2026-05-02
2026-09-26ACTIVE75.8%2026-05-02
2026-09-27ACTIVE75.8%2026-05-02
2026-09-28ACTIVE75.8%2026-05-02
2026-09-29ACTIVE75.8%2026-05-02
2026-09-30ACTIVE75.8%2026-05-02
2026-10-01ACTIVE75.8%2026-05-02
2026-10-02ACTIVE75.8%2026-05-02
2026-10-03ACTIVE75.8%2026-05-02
2026-10-04ACTIVE75.8%2026-05-02
2026-10-05ACTIVE75.8%2026-05-02
2026-10-06ACTIVE75.8%2026-05-02
2026-10-07ACTIVE75.8%2026-05-02
2026-10-08ACTIVE75.8%2026-05-02
2026-10-09ACTIVE75.8%2026-05-02
2026-10-10ACTIVE75.8%2026-05-02
2026-10-11ACTIVE75.8%2026-05-02
2026-10-12ACTIVE75.8%2026-05-02
2026-10-13ACTIVE75.8%2026-05-02
2026-10-14ACTIVE75.8%2026-05-02
2026-10-15ACTIVE75.8%2026-05-02
2026-10-16ACTIVE75.8%2026-05-02
2026-10-17ACTIVE75.8%2026-05-02
2026-10-18ACTIVE75.8%2026-05-02
2026-10-19ACTIVE75.8%2026-05-02
2026-10-20ACTIVE75.8%2026-05-02
2026-10-21ACTIVE75.8%2026-05-02
2026-10-22ACTIVE75.8%2026-05-02
2026-10-23ACTIVE75.8%2026-05-02
2026-10-24ACTIVE75.8%2026-05-02
2026-10-25ACTIVE75.8%2026-05-02
2026-10-26ACTIVE75.8%2026-05-02
2026-10-27ACTIVE75.8%2026-05-02
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.