Home / Projects / Binghatti Hillcrest
Latest DLD inspection photo of Binghatti Hillcrest
Latest inspection · 2026-09-17 · DLD inspection
Planned handover2026-12-31
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2025-10-01
in the DLD registry
Today
60.0%
last inspected 2026-09-11
At the current pace
…
…
Planned handover
2026-12-31
developer's official date

Investor snapshot — estimated yield

3.9%estimated gross rental yield

2,242/sqft median sale price (this project)

87/sqft/yr median rent in Al Barshaa South Third

Estimate: area-wide median rent ÷ this project’s median sale price, from Dubai Land Department records. Actual rent varies by unit, floor and finish.

How Binghatti Hillcrest compares

Similar off-plan projects in Al Barshaa South Third — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about Binghatti Hillcrest

Considering buying in Binghatti Hillcrest? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Watch it rise — one frame per DLD inspection

Binghatti Hillcrest on 2025-09-24
2025-09-24 · 9.3% complete
1 / 3

Building & unit mix — from DLD project records

7
Floors
396
Total units
1
Building
UsageUnit typeUnits
CommercialUnspecified28
ResidentialStudio207
Residential1 B/R157
Residential2 B/R4

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Real sale prices — 265 registered DLD sales since 2026-01-14

AED 2,242/sqft
Median sale price
265
Registered sales
265
Sales, last 12 months
Unit typeSalesMedian AED/sqftMedian price
Studio1472,261AED 824,999
1 B/R1071,798AED 1.3M
NA103,500AED 4.2M
2 B/R11,763AED 2.0M

Source: DLD registered sale transactions for this project.

Prices by unit size — vs the Al Barshaa South Third average

BedsUnits soldSize rangeMedian priceAED/sqftArea avgPremium vs area
Studio147345–729 sqftAED 824,9992,261——
1 B/R107673–1,008 sqftAED 1.3M1,798992+81%
2 B/R11,134–1,134 sqftAED 2.0M1,763——
NA10983–1,574 sqftAED 4.2M3,500——

Median AED/sqft of DLD-registered sales in this project vs all sales in Al Barshaa South Third for the same unit type. “Premium vs area” is how much more (or less) buyers pay here than the neighbourhood average.

Sale price history — 210 sales, median AED/sqft by year

+10% median price growth from 2025 to 2026 · 100% of sales were off-plan

YearMedian AED/sqftSalesYear-on-yearSince launch
2025launch1,99025——
20262,197185+10%+10%

Median AED/sqft of DLD-registered sales each year (years with 3+ sales); the earliest year on record approximates launch pricing. “Year-on-year” compares each year to the one before it, “since launch” to the first year. Source: Dubai Land Department transaction records.

Available layouts — check current availability & price

Layouts registered in Binghatti Hillcrest, grouped by size. We’ll confirm current availability, floor and price with a RERA-licensed agent — we don’t hold live developer inventory, so these are representative configurations, not a live unit list.

BedsSizeTypical priceAED/sqftRegistered
Studio362 sqftAED 815K2,25146
Studio366 sqftAED 827K2,26295
Studio392 sqftAED 863K2,2084
Studio727 sqftAED 847K1,1662
1 B/R681 sqftAED 1.4M1,9928
1 B/R699 sqftAED 1.3M1,91214
1 B/R715 sqftAED 1.3M1,84540
1 B/R748 sqftAED 1.3M1,7589
1 B/R794 sqftAED 1.4M1,7556
1 B/R821 sqftAED 1.4M1,7635
1 B/R878 sqftAED 1.5M1,6688
1 B/R924 sqftAED 1.5M1,6133
1 B/R941 sqftAED 1.4M1,5351
1 B/R980 sqftAED 1.2M1,1993

Recent registered sales — individual DLD transactions, newest first

DateBedsSizePriceAED/sqftType
2026-11-031 B/R1,008 sqftAED 1.4M1,404Off-plan
2026-11-03Studio729 sqftAED 879,9991,208Off-plan
2026-11-02Studio362 sqftAED 819,9992,265Off-plan
2026-11-01Studio366 sqftAED 828,9992,267Off-plan
2026-11-01Studio386 sqftAED 879,9992,277Off-plan
2026-11-01Studio364 sqftAED 823,9992,261Off-plan
2026-10-292 B/R1,134 sqftAED 2.0M1,763Off-plan
2026-10-29Studio364 sqftAED 819,9992,250Off-plan
2026-10-29Studio366 sqftAED 824,9992,254Off-plan
2026-10-28Studio364 sqftAED 821,9992,257Off-plan
2026-10-27Studio364 sqftAED 821,9992,255Off-plan
2026-10-22Studio364 sqftAED 821,9992,256Off-plan
2026-10-22Studio366 sqftAED 826,9992,262Off-plan
2026-10-22Studio369 sqftAED 827,9992,245Off-plan
2026-10-22Studio362 sqftAED 811,9992,245Off-plan
2026-10-20Studio362 sqftAED 814,9992,251Off-plan
2026-10-191 B/R980 sqftAED 1.1M1,122Off-plan
2026-10-19Studio362 sqftAED 816,9992,255Off-plan
2026-10-19Studio364 sqftAED 822,9992,262Off-plan
2026-10-191 B/R794 sqftAED 1.4M1,754Off-plan
2026-10-19Studio390 sqftAED 814,9992,088Off-plan
2026-10-19Studio366 sqftAED 824,9992,254Off-plan
2026-10-18Studio364 sqftAED 821,9992,255Off-plan
2026-10-161 B/R1,001 sqftAED 1.1M1,099Off-plan
2026-10-151 B/R751 sqftAED 1.3M1,798Off-plan
2026-10-141 B/R713 sqftAED 1.2M1,648Off-plan
2026-10-13Studio360 sqftAED 799,9992,225Off-plan
2026-10-13Studio369 sqftAED 828,9992,248Off-plan
2026-10-13Studio365 sqftAED 825,9992,263Off-plan
2026-10-13Studio362 sqftAED 808,9992,237Off-plan
2026-10-13Studio362 sqftAED 808,9992,237Off-plan
2026-10-12Studio367 sqftAED 819,9992,236Off-plan
2026-10-12Studio362 sqftAED 808,9992,237Off-plan
2026-10-121 B/R715 sqftAED 1.2M1,643Off-plan
2026-10-09Studio364 sqftAED 821,9992,255Off-plan
2026-10-09Studio364 sqftAED 821,9992,255Off-plan
2026-10-09Studio361 sqftAED 854,9992,368Off-plan
2026-10-09Studio363 sqftAED 823,9992,268Off-plan
2026-10-091 B/R998 sqftAED 1.1M1,102Off-plan
2026-10-09Studio366 sqftAED 826,9992,262Off-plan

Source: DLD registered sale transactions. Floor and unit numbers aren’t published in the public transaction feed, so they’re not shown.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
Binghatti Developers FZE
Area
Al Barshaa South Third
Master project
—
Project type
Normal
Start date
2025-10-01
Planned handover
2026-12-31
Last inspection
2026-09-11
Project value
AED 135.0M
Units
396
Villas
0
Buildings
0
DLD project number
4105

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
4105
Registered with DLD
2025-12-09
Regulator
Dubai Development Authority (DDA)
Escrow account no.
0011370621106

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Al Barshaa South Third · See every project on the construction map →

Binghatti Hillcrest: frequently asked questions — answers update daily from registry data

When will Binghatti Hillcrest be handed over?
The developer's planned handover for Binghatti Hillcrest is 2026-12-31; construction is currently 60% complete. At the observed construction pace, our independent forecast is 2027-11-14.
How far along is construction on Binghatti Hillcrest?
Binghatti Hillcrest is 60.0% complete according to the Dubai Land Department's inspection of 2026-09-11.
Is Binghatti Hillcrest delayed?
As of today, Binghatti Hillcrest has not passed its planned handover date of 2026-12-31. We compare the official date against the calendar daily and record every change on this page.
Who is the developer of Binghatti Hillcrest, and do they deliver on time?
Binghatti Hillcrest is developed by Binghatti Developers FZE. On our Developer Reliability Index they score 66/100 (C — Slipping), based on how much of their active portfolio is past its planned handover in the official registry.
What are real sale prices in Binghatti Hillcrest?
Registered DLD sales in Binghatti Hillcrest show a median of AED 2,242/sqft across 265 transactions since 2026-01-14. These are actual registered sales, not asking prices — the full breakdown is on this page.
Where is Binghatti Hillcrest located?
Binghatti Hillcrest is located in Al Barshaa South Third, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Binghatti Hillcrest?
Binghatti Hillcrest comprises 396 units (normal), per the DLD registry.
Can I see real construction photos of Binghatti Hillcrest?
Yes — this page carries 33 official construction photos taken during Dubai Land Department inspections, newest from 2026-09-17, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in Binghatti Hillcrest?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for Binghatti Hillcrest go?
Only into the project's DLD-registered escrow account (no. 0011370621106). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on Binghatti Hillcrest?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Binghatti Hillcrest's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE50.2%2026-12-31
2026-08-05ACTIVE50.2%2026-12-31
2026-08-06ACTIVE50.2%2026-12-31
2026-08-08ACTIVE50.2%2026-12-31
2026-08-09ACTIVE50.2%2026-12-31
2026-08-10ACTIVE50.2%2026-12-31
2026-08-11ACTIVE50.2%2026-12-31
2026-08-12ACTIVE50.2%2026-12-31
2026-08-13ACTIVE50.2%2026-12-31
2026-08-14ACTIVE50.2%2026-12-31
2026-08-15ACTIVE50.2%2026-12-31
2026-08-16ACTIVE50.2%2026-12-31
2026-08-17ACTIVE50.2%2026-12-31
2026-08-18ACTIVE50.2%2026-12-31
2026-08-19ACTIVE50.2%2026-12-31
2026-08-20ACTIVE50.2%2026-12-31
2026-08-21ACTIVE50.2%2026-12-31
2026-08-22ACTIVE50.2%2026-12-31
2026-08-23ACTIVE50.2%2026-12-31
2026-08-24ACTIVE50.2%2026-12-31
2026-08-25ACTIVE50.2%2026-12-31
2026-08-26ACTIVE50.2%2026-12-31
2026-08-27ACTIVE50.2%2026-12-31
2026-08-28ACTIVE50.2%2026-12-31
2026-08-29ACTIVE50.2%2026-12-31
2026-08-30ACTIVE50.2%2026-12-31
2026-08-31ACTIVE50.2%2026-12-31
2026-09-01ACTIVE50.2%2026-12-31
2026-09-02ACTIVE50.2%2026-12-31
2026-09-03ACTIVE50.2%2026-12-31
2026-09-04ACTIVE50.2%2026-12-31
2026-09-05ACTIVE50.2%2026-12-31
2026-09-06ACTIVE50.2%2026-12-31
2026-09-07ACTIVE50.2%2026-12-31
2026-09-08ACTIVE50.2%2026-12-31
2026-09-09ACTIVE50.2%2026-12-31
2026-09-10ACTIVE50.2%2026-12-31
2026-09-11ACTIVE50.2%2026-12-31
2026-09-12ACTIVE50.2%2026-12-31
2026-09-13ACTIVE50.2%2026-12-31
2026-09-14ACTIVE50.2%2026-12-31
2026-09-15ACTIVE50.2%2026-12-31
2026-09-16ACTIVE50.2%2026-12-31
2026-09-17ACTIVE50.2%2026-12-31
2026-09-18ACTIVE50.2%2026-12-31
2026-09-19ACTIVE50.2%2026-12-31
2026-09-20ACTIVE50.2%2026-12-31
2026-09-21ACTIVE50.2%2026-12-31
2026-09-22ACTIVE60.0%2026-12-31
2026-09-23ACTIVE60.0%2026-12-31
2026-09-24ACTIVE60.0%2026-12-31
2026-09-25ACTIVE60.0%2026-12-31
2026-09-26ACTIVE60.0%2026-12-31
2026-09-27ACTIVE60.0%2026-12-31
2026-09-28ACTIVE60.0%2026-12-31
2026-09-29ACTIVE60.0%2026-12-31
2026-09-30ACTIVE60.0%2026-12-31
2026-10-01ACTIVE60.0%2026-12-31
2026-10-02ACTIVE60.0%2026-12-31
2026-10-03ACTIVE60.0%2026-12-31
2026-10-04ACTIVE60.0%2026-12-31
2026-10-05ACTIVE60.0%2026-12-31
2026-10-06ACTIVE60.0%2026-12-31
2026-10-07ACTIVE60.0%2026-12-31
2026-10-08ACTIVE60.0%2026-12-31
2026-10-09ACTIVE60.0%2026-12-31
2026-10-10ACTIVE60.0%2026-12-31
2026-10-11ACTIVE60.0%2026-12-31
2026-10-12ACTIVE60.0%2026-12-31
2026-10-13ACTIVE60.0%2026-12-31
2026-10-14ACTIVE60.0%2026-12-31
2026-10-15ACTIVE60.0%2026-12-31
2026-10-16ACTIVE60.0%2026-12-31
2026-10-17ACTIVE60.0%2026-12-31
2026-10-18ACTIVE60.0%2026-12-31
2026-10-19ACTIVE60.0%2026-12-31
2026-10-20ACTIVE60.0%2026-12-31
2026-10-21ACTIVE60.0%2026-12-31
2026-10-22ACTIVE60.0%2026-12-31
2026-10-23ACTIVE60.0%2026-12-31
2026-10-24ACTIVE60.0%2026-12-31
2026-10-25ACTIVE60.0%2026-12-31
2026-10-26ACTIVE60.0%2026-12-31
2026-10-27ACTIVE60.0%2026-12-31
2026-10-28ACTIVE60.0%2026-12-31
2026-10-29ACTIVE60.0%2026-12-31
2026-10-30ACTIVE60.0%2026-12-31
2026-10-31ACTIVE60.0%2026-12-31
2026-11-01ACTIVE60.0%2026-12-31
2026-11-02ACTIVE60.0%2026-12-31
2026-11-03ACTIVE60.0%2026-12-31
2026-11-04ACTIVE60.0%2026-12-31

Change events

DetectedEventChange
2026-09-22PROGRESS50.23 → 60.00
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.
Track Binghatti Hillcrest