Home / Projects / Zenith Tower J1
Latest DLD inspection photo of Zenith Tower J1
Latest inspection · 2026-08-04 · DLD inspection
Planned handover2026-12-25
SourceDLD · daily

The road to keys — registry facts, our forecast

Registered start
2023-09-27
in the DLD registry
Today
72.2%
last inspected 2026-07-25
At the current pace
Planned handover
2026-12-25
developer's official date

Investor snapshot — estimated yield

5.0%estimated gross rental yield

1,775/sqft median sale price (this project)

89/sqft/yr median rent in Al Barsha South Fourth

Estimate: area-wide median rent ÷ this project’s median sale price, from Dubai Land Department records. Actual rent varies by unit, floor and finish.

How Zenith Tower J1 compares

Similar off-plan projects in Al Barsha South Fourth — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about Zenith Tower J1

Considering buying in Zenith Tower J1? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Watch it rise — one frame per DLD inspection

Zenith Tower J1 on 2025-05-08
2025-05-08 · 36.8% complete
1 / 3

Building & unit mix — from DLD project records

15
Floors
76
Total units
1
Building
UsageUnit typeUnits
CommercialUnspecified15
Residential1 B/R29
Residential2 B/R12
Residential3 B/R20

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Real sale prices 4 registered DLD sales since 2026-07-15

AED 1,775/sqft
Median sale price
4
Registered sales
4
Sales, last 12 months
Unit typeSalesMedian AED/sqftMedian price
1 B/R31,779AED 2.2M
3 B/R11,506AED 2.4M

Source: DLD registered sale transactions for this project.

Prices by unit size — vs the Al Barsha South Fourth average

BedsUnits soldSize rangeMedian priceAED/sqftArea avgPremium vs area
1 B/R38021,233 sqftAED 2.2M1,779
3 B/R11,5941,594 sqftAED 2.4M1,506

Median AED/sqft of DLD-registered sales in this project vs all sales in Al Barsha South Fourth for the same unit type. “Premium vs area” is how much more (or less) buyers pay here than the neighbourhood average.

Available layouts — check current availability & price

Layouts registered in Zenith Tower J1, grouped by size. We’ll confirm current availability, floor and price with a RERA-licensed agent — we don’t hold live developer inventory, so these are representative configurations, not a live unit list.

BedsSizeTypical priceAED/sqftRegistered
1 B/R802 sqftAED 1.5M1,8751
1 B/R1,229 sqftAED 2.2M1,7752
3 B/R1,594 sqftAED 2.4M1,5061

Recent registered sales — individual DLD transactions, newest first

DateBedsSizePriceAED/sqftType
2026-09-141 B/R1,225 sqftAED 2.2M1,779Off-plan
2026-09-113 B/R1,594 sqftAED 2.4M1,506Off-plan
2026-08-101 B/R802 sqftAED 1.5M1,875Off-plan
2026-07-151 B/R1,233 sqftAED 2.2M1,772Off-plan

Source: DLD registered sale transactions. Floor and unit numbers aren’t published in the public transaction feed, so they’re not shown.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
ZENITH VENTURES REAL ESTATE DEVELOPMENT L.L.C
Area
Al Barsha South Fourth
Master project
Project type
Normal
Start date
2023-09-27
Planned handover
2026-12-25
Last inspection
2026-07-25
Project value
AED 67.9M
Units
76
Villas
0
Buildings
0
DLD project number
3628

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
3628
Registered with DLD
2025-09-10
Regulator
Trakhees
Escrow account no.
14200413920002

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Al Barsha South Fourth · See every project on the construction map →

Zenith Tower J1: frequently asked questions — answers update daily from registry data

When will Zenith Tower J1 be handed over?
The developer's planned handover for Zenith Tower J1 is 2026-12-25; construction is currently 72% complete. At the observed construction pace, our independent forecast is 2026-12-06.
How far along is construction on Zenith Tower J1?
Zenith Tower J1 is 72.2% complete according to the Dubai Land Department's inspection of 2026-07-25.
Is Zenith Tower J1 delayed?
As of today, Zenith Tower J1 has not passed its planned handover date of 2026-12-25. We compare the official date against the calendar daily and record every change on this page.
Who is the developer of Zenith Tower J1, and do they deliver on time?
Zenith Tower J1 is developed by ZENITH VENTURES REAL ESTATE DEVELOPMENT L.L.C. On our Developer Reliability Index they score 89/100 (A On schedule), based on how much of their active portfolio is past its planned handover in the official registry.
What are real sale prices in Zenith Tower J1?
Registered DLD sales in Zenith Tower J1 show a median of AED 1,775/sqft across 4 transactions since 2026-07-15. These are actual registered sales, not asking prices — the full breakdown is on this page.
Where is Zenith Tower J1 located?
Zenith Tower J1 is located in Al Barsha South Fourth, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Zenith Tower J1?
Zenith Tower J1 comprises 76 units (normal), per the DLD registry.
Can I see real construction photos of Zenith Tower J1?
Yes — this page carries 28 official construction photos taken during Dubai Land Department inspections, newest from 2026-08-04, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in Zenith Tower J1?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for Zenith Tower J1 go?
Only into the project's DLD-registered escrow account (no. 14200413920002). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on Zenith Tower J1?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Zenith Tower J1's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE55.4%2026-12-25
2026-08-05ACTIVE55.4%2026-12-25
2026-08-06ACTIVE55.4%2026-12-25
2026-08-08ACTIVE72.2%2026-12-25
2026-08-09ACTIVE72.2%2026-12-25
2026-08-10ACTIVE72.2%2026-12-25
2026-08-11ACTIVE72.2%2026-12-25
2026-08-12ACTIVE72.2%2026-12-25
2026-08-13ACTIVE72.2%2026-12-25
2026-08-14ACTIVE72.2%2026-12-25
2026-08-15ACTIVE72.2%2026-12-25
2026-08-16ACTIVE72.2%2026-12-25
2026-08-17ACTIVE72.2%2026-12-25
2026-08-18ACTIVE72.2%2026-12-25
2026-08-19ACTIVE72.2%2026-12-25
2026-08-20ACTIVE72.2%2026-12-25
2026-08-21ACTIVE72.2%2026-12-25
2026-08-22ACTIVE72.2%2026-12-25
2026-08-23ACTIVE72.2%2026-12-25
2026-08-24ACTIVE72.2%2026-12-25
2026-08-25ACTIVE72.2%2026-12-25
2026-08-26ACTIVE72.2%2026-12-25
2026-08-27ACTIVE72.2%2026-12-25
2026-08-28ACTIVE72.2%2026-12-25
2026-08-29ACTIVE72.2%2026-12-25
2026-08-30ACTIVE72.2%2026-12-25
2026-08-31ACTIVE72.2%2026-12-25
2026-09-01ACTIVE72.2%2026-12-25
2026-09-02ACTIVE72.2%2026-12-25
2026-09-03ACTIVE72.2%2026-12-25
2026-09-04ACTIVE72.2%2026-12-25
2026-09-05ACTIVE72.2%2026-12-25
2026-09-06ACTIVE72.2%2026-12-25
2026-09-07ACTIVE72.2%2026-12-25
2026-09-08ACTIVE72.2%2026-12-25
2026-09-09ACTIVE72.2%2026-12-25
2026-09-10ACTIVE72.2%2026-12-25
2026-09-11ACTIVE72.2%2026-12-25
2026-09-12ACTIVE72.2%2026-12-25
2026-09-13ACTIVE72.2%2026-12-25
2026-09-14ACTIVE72.2%2026-12-25
2026-09-15ACTIVE72.2%2026-12-25
2026-09-16ACTIVE72.2%2026-12-25
2026-09-17ACTIVE72.2%2026-12-25
2026-09-18ACTIVE72.2%2026-12-25
2026-09-19ACTIVE72.2%2026-12-25
2026-09-20ACTIVE72.2%2026-12-25

Change events

DetectedEventChange
2026-08-08PROGRESS55.4272.24
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.