The road to keys — registry facts, our forecast

Registered start
2023-06-01
in the DLD registry
Today
91.2%
last inspected 2026-08-13
At the current pace
Planned handover
2026-01-31
232 days overdue — developer's official date

Investor snapshot — estimated yield

4.6%estimated gross rental yield

1,797/sqft median sale price (this project)

82/sqft/yr median rent in Madinat Al Mataar

Estimate: area-wide median rent ÷ this project’s median sale price, from Dubai Land Department records. Actual rent varies by unit, floor and finish.

How Expo City Mangrove Residences compares

Similar off-plan projects in Madinat Al Mataar — compare progress, handover and developer.

Ready to take the next step?

Talk to a verified agent about Expo City Mangrove Residences

Considering buying in Expo City Mangrove Residences? Register your interest and we’ll connect you with a RERA-licensed Dubai agent who can walk you through availability, payment plans and resale value — alongside the honest, registry-backed data you see on this page. No obligation.

or register your interest below

By submitting, you agree to be contacted about this project. We only introduce currently RERA-licensed agents.

Watch it rise — one frame per DLD inspection

Expo City Mangrove Residences on 2023-03-17
2023-03-17 · 0.0% complete
1 / 9

Building & unit mix — from DLD project records

20
Floors
470
Total units
3
Buildings
UsageUnit typeUnits
CommercialUnspecified20
Residential1 B/R114
Residential2 B/R264
Residential3 B/R68
Residential4 B/R4

Source: DLD project register — floors, buildings and the developer's registered unit mix.

Real sale prices 27 registered DLD sales since 2026-01-05

AED 1,797/sqft
Median sale price
27
Registered sales
27
Sales, last 12 months
Unit typeSalesMedian AED/sqftMedian price
2 B/R211,724AED 2.5M
1 B/R51,960AED 1.9M
4 B/R12,100AED 8.6M

Source: DLD registered sale transactions for this project.

Prices by unit size — vs the Madinat Al Mataar average

BedsUnits soldSize rangeMedian priceAED/sqftArea avgPremium vs area
1 B/R5970985 sqftAED 1.9M1,9601,609+22%
2 B/R211,3771,491 sqftAED 2.5M1,7241,604+8%
4 B/R14,0854,085 sqftAED 8.6M2,1001,299+62%

Median AED/sqft of DLD-registered sales in this project vs all sales in Madinat Al Mataar for the same unit type. “Premium vs area” is how much more (or less) buyers pay here than the neighbourhood average.

Sale price history 508 sales, median AED/sqft by year

+13% median price growth from 2023 to 2026 · 100% of sales were off-plan

YearMedian AED/sqftSalesYear-on-yearSince launch
2023launch1,630348
20241,65989+2%+2%
20251,95050+18%+20%
20261,84921-5%+13%

Median AED/sqft of DLD-registered sales each year (years with 3+ sales); the earliest year on record approximates launch pricing. “Year-on-year” compares each year to the one before it, “since launch” to the first year. Source: Dubai Land Department transaction records.

Available layouts — check current availability & price

Layouts registered in Expo City Mangrove Residences, grouped by size. We’ll confirm current availability, floor and price with a RERA-licensed agent — we don’t hold live developer inventory, so these are representative configurations, not a live unit list.

BedsSizeTypical priceAED/sqftRegistered
1 B/R970 sqftAED 1.9M1,9605
2 B/R1,377 sqftAED 2.4M1,74412
2 B/R1,422 sqftAED 2.5M1,7576
2 B/R1,490 sqftAED 2.5M1,6873
4 B/R4,085 sqftAED 8.6M2,1001

Recent registered sales — individual DLD transactions, newest first

DateBedsSizePriceAED/sqftType
2026-09-162 B/R1,377 sqftAED 2.3M1,670Off-plan
2026-09-012 B/R1,423 sqftAED 2.5M1,789Off-plan
2026-08-262 B/R1,423 sqftAED 2.4M1,652Off-plan
2026-08-132 B/R1,490 sqftAED 2.5M1,687Off-plan
2026-08-122 B/R1,378 sqftAED 2.3M1,687Off-plan
2026-08-112 B/R1,378 sqftAED 2.3M1,704Off-plan
2026-07-212 B/R1,377 sqftAED 2.3M1,652Off-plan
2026-06-302 B/R1,420 sqftAED 2.4M1,724Off-plan
2026-06-242 B/R1,420 sqftAED 2.6M1,849Off-plan
2026-06-232 B/R1,377 sqftAED 2.5M1,785Off-plan
2026-06-162 B/R1,378 sqftAED 2.3M1,684Off-plan
2026-06-041 B/R970 sqftAED 1.8M1,857Off-plan
2026-06-022 B/R1,379 sqftAED 2.6M1,921Off-plan
2026-05-232 B/R1,423 sqftAED 2.3M1,620Off-plan
2026-05-112 B/R1,377 sqftAED 2.3M1,670Off-plan
2026-04-282 B/R1,491 sqftAED 2.3M1,509Off-plan
2026-04-221 B/R970 sqftAED 1.8M1,805Off-plan
2026-04-134 B/R4,085 sqftAED 8.6M2,100Off-plan
2026-03-122 B/R1,490 sqftAED 2.7M1,814Off-plan
2026-03-122 B/R1,379 sqftAED 3.0M2,139Off-plan
2026-03-022 B/R1,421 sqftAED 2.9M2,026Off-plan
2026-02-202 B/R1,377 sqftAED 2.7M1,975Off-plan
2026-02-162 B/R1,377 sqftAED 2.6M1,924Off-plan
2026-02-152 B/R1,377 sqftAED 2.5M1,797Off-plan
2026-02-061 B/R970 sqftAED 1.9M1,960Off-plan
2026-01-051 B/R970 sqftAED 2.0M2,114Off-plan
2026-01-051 B/R985 sqftAED 2.0M1,990Off-plan

Source: DLD registered sale transactions. Floor and unit numbers aren’t published in the public transaction feed, so they’re not shown.

Construction photos — official DLD inspection uploads, newest first

Project facts

Developer
Expo City Mangrove Residences Development FZCO
Area
Madinat Al Mataar
Master project
Project type
Normal
Start date
2023-06-01
Planned handover
2026-01-31
Last inspection
2026-08-13
Project value
AED 589.3M
Units
470
Villas
0
Buildings
0
DLD project number
2612

Registration & escrow — verify before you pay anyone

DLD / RERA project no.
2612
Registered with DLD
2023-04-04
Regulator
Dubai Municipality
Escrow account no.
001582318250401

Under Law 8 of 2007, off-plan payments for this project belong only in the escrow account above — a developer or agent directing your money anywhere else is a serious red flag. How escrow protects you →

Location — official site coordinates from DLD inspection records

Loading map…

Madinat Al Mataar · See every project on the construction map →

Expo City Mangrove Residences: frequently asked questions — answers update daily from registry data

When will Expo City Mangrove Residences be handed over?
The developer's planned handover for Expo City Mangrove Residences is 2026-01-31; construction is currently 91% complete. At the observed construction pace, our independent forecast is 2026-11-05.
How far along is construction on Expo City Mangrove Residences?
Expo City Mangrove Residences is 91.2% complete according to the Dubai Land Department's inspection of 2026-08-13.
Is Expo City Mangrove Residences delayed?
Expo City Mangrove Residences is 232 days past its planned handover of 2026-01-31 and still under construction. Most Dubai off-plan contracts include a grace period (often 6–12 months) beyond the anticipated date — see The Late List for how it compares.
Who is the developer of Expo City Mangrove Residences, and do they deliver on time?
Expo City Mangrove Residences is developed by Expo City Mangrove Residences Development FZCO. On our Developer Reliability Index they score 67/100 (C Slipping), based on how much of their active portfolio is past its planned handover in the official registry.
What are real sale prices in Expo City Mangrove Residences?
Registered DLD sales in Expo City Mangrove Residences show a median of AED 1,797/sqft across 27 transactions since 2026-01-05. These are actual registered sales, not asking prices — the full breakdown is on this page.
Where is Expo City Mangrove Residences located?
Expo City Mangrove Residences is located in Madinat Al Mataar, Dubai. See every project in the area, plus prices and rents, on the area page.
How many homes are in Expo City Mangrove Residences?
Expo City Mangrove Residences comprises 470 units (normal), per the DLD registry.
Can I see real construction photos of Expo City Mangrove Residences?
Yes — this page carries 65 official construction photos taken during Dubai Land Department inspections, newest from 2026-08-18, plus a time-lapse of the build. These are government inspection uploads, not marketing renders.
Is my money safe if I buy in Expo City Mangrove Residences?
Payments for registered Dubai off-plan projects go into a project-specific escrow account under Law No. 8 of 2007; the developer can only draw funds against certified construction milestones.
Where should payments for Expo City Mangrove Residences go?
Only into the project's DLD-registered escrow account (no. 001582318250401). Under Law 8 of 2007 every off-plan payment must go to this account, where the developer can only draw funds as construction milestones are certified. Anyone directing payments elsewhere is a serious warning sign.
How do I get alerts when something changes on Expo City Mangrove Residences?
Use the free Track this project form on this page. We check the official registry every day and email you the moment Expo City Mangrove Residences's progress, status, or planned handover date changes.

Progress history — one row per official DLD snapshot

Snapshot dateStatusCompletePlanned handover
2026-08-04ACTIVE82.3%2026-01-31
2026-08-05ACTIVE82.3%2026-01-31
2026-08-06ACTIVE82.3%2026-01-31
2026-08-08ACTIVE82.3%2026-01-31
2026-08-09ACTIVE82.3%2026-01-31
2026-08-10ACTIVE82.3%2026-01-31
2026-08-11ACTIVE82.3%2026-01-31
2026-08-12ACTIVE82.3%2026-01-31
2026-08-13ACTIVE82.3%2026-01-31
2026-08-14ACTIVE82.3%2026-01-31
2026-08-15ACTIVE82.3%2026-01-31
2026-08-16ACTIVE82.3%2026-01-31
2026-08-17ACTIVE82.3%2026-01-31
2026-08-18ACTIVE82.3%2026-01-31
2026-08-19ACTIVE82.3%2026-01-31
2026-08-20ACTIVE82.3%2026-01-31
2026-08-21ACTIVE82.3%2026-01-31
2026-08-22ACTIVE82.3%2026-01-31
2026-08-23ACTIVE82.3%2026-01-31
2026-08-24ACTIVE82.3%2026-01-31
2026-08-25ACTIVE91.2%2026-01-31
2026-08-26ACTIVE91.2%2026-01-31
2026-08-27ACTIVE91.2%2026-01-31
2026-08-28ACTIVE91.2%2026-01-31
2026-08-29ACTIVE91.2%2026-01-31
2026-08-30ACTIVE91.2%2026-01-31
2026-08-31ACTIVE91.2%2026-01-31
2026-09-01ACTIVE91.2%2026-01-31
2026-09-02ACTIVE91.2%2026-01-31
2026-09-03ACTIVE91.2%2026-01-31
2026-09-04ACTIVE91.2%2026-01-31
2026-09-05ACTIVE91.2%2026-01-31
2026-09-06ACTIVE91.2%2026-01-31
2026-09-07ACTIVE91.2%2026-01-31
2026-09-08ACTIVE91.2%2026-01-31
2026-09-09ACTIVE91.2%2026-01-31
2026-09-10ACTIVE91.2%2026-01-31
2026-09-11ACTIVE91.2%2026-01-31
2026-09-12ACTIVE91.2%2026-01-31
2026-09-13ACTIVE91.2%2026-01-31
2026-09-14ACTIVE91.2%2026-01-31
2026-09-15ACTIVE91.2%2026-01-31
2026-09-16ACTIVE91.2%2026-01-31
2026-09-17ACTIVE91.2%2026-01-31
2026-09-18ACTIVE91.2%2026-01-31
2026-09-19ACTIVE91.2%2026-01-31
2026-09-20ACTIVE91.2%2026-01-31

Change events

DetectedEventChange
2026-08-25PROGRESS82.2591.16
Don't check back — we'll tell you.Progress moves, dates slip, statuses change. One email the moment it happens.
Track Expo City Mangrove Residences